546 N GARDNER ST 90036
Certificate Information: 546 N GARDNER ST 90036
- Application / Permit
- 21014-20001-04088
- Plan Check / Job No.
- B24VN00435
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPP. TO 21014-20000-04088 TO REVISE PLAN AND FOUNDATIONS ( see comment)
- Permit Issued
- Issued on 1/17/2024
- Issuing Office
- Valley
- Current Status
- Permit Finaled on 3/12/2026
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 1/12/2024 | APPLICANT |
| Assigned to Plan Check Engineer | 1/12/2024 | MOHAMMAD ESMAILI |
| Plan Check Approved | 1/12/2024 | MOHAMMAD ESMAILI |
| Issued | 1/17/2024 | APPLICANT |
| Permit Finaled | 3/11/2026 | JOSH MEISTER |
Permit Application Clearance Information
| No Data Available. |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Lotfi,, Fariborz Frank; Lic. No.: C49359 | 1328 DUENDE LANE PACIFIC PALISADES, CA 90272 |
Inspector Information
| JOSE MACIAS, (213) 202-3125 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/22/2024 | Partial Inspection | LILIANA PORTILLO |
| Excavation/Setback/Form/Re-Bar | 3/14/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Pre-Inspection | 3/14/2024 | Partial Inspection | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 4/4/2024 | Corrections Issued | AMIR NAZARIAN |
| Footing/Foundation/Slab | 4/4/2024 | Corrections Issued | AMIR NAZARIAN |
| Excavation/Setback/Form/Re-Bar | 4/8/2024 | Partial Approval | AMIR NAZARIAN |
| Footing/Foundation/Slab | 4/8/2024 | Partial Approval | AMIR NAZARIAN |
| Pre-Inspection | 6/11/2024 | Approved | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/16/2024 | Corrections Issued | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Partial Approval | AMIR NAZARIAN |
| Wood Frame | 8/1/2024 | Not Ready for Inspection | AMIR NAZARIAN |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2025 | Corrections Issued | JOSE MACIAS |
| Floor/Roof Diaphrgm/Shear Wall | 1/31/2025 | Corrections Issued | JOSE MACIAS |
| Interior/Exterior Lathing | 9/16/2025 | Partial Approval | JOSE MACIAS |
| Insulation | 10/3/2025 | Corrections Issued | DEVON JACKSON |
| Insulation | 10/9/2025 | No Access for Inspection | ENRIQUE MIRELES |
| Insulation | 10/16/2025 | Conditional Approval | JOSH MEISTER |
| Wood Frame | 10/16/2025 | Conditional Approval | JOSH MEISTER |
| Drywall Nailing | 10/22/2025 | Not Ready for Inspection | JOSH MEISTER |
| Verify Sprinkler Sign Off | 10/22/2025 | Approved | JOSH MEISTER |
| Drywall Nailing | 10/24/2025 | Approved | ALEX COLIN |
| Interior/Exterior Lathing | 11/19/2025 | Approved | JOSH MEISTER |
| Final | 3/11/2026 | Permit Finaled | JOSH MEISTER |
| Smoke Detectors | 3/11/2026 | Approved | JOSH MEISTER |