3153 S MOUNTAIN VIEW AVE 90066
Certificate Information: 3153 S MOUNTAIN VIEW AVE 90066
- Application / Permit
- 21014-20001-03755
- Plan Check / Job No.
- B22VN05211
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT TO 21014-30000-03755 TO ADD 139.5 SQ. FT. TO THE KITCHEN AND REVISE INTERIOR. CHANGE OF ENGINEER OF RECORD. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 5/3/2022
- Issuing Office
- Current Status
- Permit Finaled on 6/4/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 4/6/2022 | APPLICANT |
| Plan Check Approved | 4/26/2022 | COLIN LOREDO |
| Assigned to Plan Check Engineer | 4/27/2022 | COLIN LOREDO |
| Issued | 5/3/2022 | APPLICANT |
| Permit Finaled | 6/4/2024 | JESUS PINEDA |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 4/9/2022 | SAUL GARCIA |
| Roof/Waste drainage to street | Cleared | 4/9/2022 | SAUL GARCIA |
| Grading Pre-Inspection | Cleared | 4/12/2022 | ROBERT HUGHES |
Contact Information
| Architect | Mcvay,, Bruce Cameron; Lic. No.: C11870 | 6440 E. EL ROBLE STREET LONG BEACH, CA 90815 |
| Contractor | Owner-Builder | , |
Inspector Information
| KIRK SANDERS, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
| ARAM AVEDISIAN, (310) 914-3896 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/6/2022 | Approved | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/14/2022 | Partial Approval | JOHNNY MIRANDA |
| PLUMBING-Rough | 6/14/2022 | Partial Approval | JOHNNY MIRANDA |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Partial Approval | JOHNNY MIRANDA |
| Wood Frame | 8/2/2022 | Approved | JOHN KIDWELL |
| Floor/Roof Diaphrgm/Shear Wall | 8/9/2022 | Approved | JOHNNY MIRANDA |
| Green Building Rough | 8/9/2022 | Not Ready for Inspection | JOHNNY MIRANDA |
| BUILDING-Rough-Frame | 12/13/2022 | Partial Approval | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 1/5/2023 | Corrections Issued | JOHNNY MIRANDA |
| PLUMBING-Rough | 1/5/2023 | Corrections Issued | JOHNNY MIRANDA |
| ELECTRICAL-Rough | 7/6/2023 | Not Ready for Inspection | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 7/6/2023 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 7/6/2023 | Not Ready for Inspection | JESUS PINEDA |
| ELECTRICAL-Rough | 7/11/2023 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 7/11/2023 | Approved | JESUS PINEDA |
| BUILDING-Rough-Frame | 8/17/2023 | Approved | JESUS PINEDA |
| Green Building Rough | 8/17/2023 | Approved | JESUS PINEDA |
| Insulation | 8/17/2023 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 8/17/2023 | Approved | JESUS PINEDA |