759 E 25TH ST 90011

Certificate Information: 759 E 25TH ST 90011

Application / Permit
21014-20001-03501
Plan Check / Job No.
B22VN16427
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
SUPPLEMENTAL TO 21014-20000-03501 - REVISE SCOPE OF WORK TO (N) 37' X 69'-11" 2-STORY DUPLEX. NFPA-13D SPRINKLERS REQUIRED. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 11/29/2023
Issuing Office
Valley
Current Status
Permit Finaled on 2/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2022 APPLICANT
Assigned to Plan Check Engineer 11/9/2022 RAPHAEL ROSAS
Plans on Hold 11/10/2022 OMID HEDAYAT
Hold Released 12/2/2022 OMID HEDAYAT
Corrections Issued 12/8/2022 RAPHAEL ROSAS
Quality Review Completed 12/12/2022 STEVEN KIM
Building Plans Picked Up 12/14/2022 APPLICANT
Applicant returned to address corrections 1/18/2023 RAPHAEL ROSAS
Applicant returned to address corrections 1/30/2023 RAPHAEL ROSAS
Plan Check Approved 10/23/2023 RAPHAEL ROSAS
Plan Check Approved 11/28/2023 RAPHAEL ROSAS
Issued 11/29/2023 APPLICANT
Permit Finaled 2/4/2025 ALEJANDRO DE ARTOLA

Permit Application Clearance Information

Address approval Cleared 2/6/2023 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 2/6/2023 JEANETTE VONG
Permit Cleared 2/6/2023 JEANETTE VONG
Sewer availability Cleared 2/6/2023 JEANETTE VONG
Tenant Habitability Plan Cleared 2/6/2023 MICHAEL SOTO
Hydrant and Access approval Cleared 2/9/2023 GILBERT URREA
Low Impact Development Cleared 2/13/2023 ERNEST TSE
Roof/Waste drainage to street Cleared 2/21/2023 JEANETTE VONG
Trees in Parkway Cleared 3/1/2023 ADALBERTO VERA
SB8 RUD Cleared 10/12/2023 LOUIE MILLER

Contact Information

Contractor Urban Kikoli; Lic. No.: 1011500-B 202 N LAPEER DRIVE UNIT 2      BEVERLY HILLS, CA 90211
Engineer Sadjadi,, Abdulreza; Lic. No.: C51812 1223 WILSHIRE BLVD #169      SANTA MONICA, CA 90403

Inspector Information

ALEJANDRO DE ARTOLA, (213) 202-3128 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/10/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 2/15/2024 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/1/2024 Partial Approval ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 3/20/2024 Partial Inspection JOSEPH MCGARRY
Footing/Foundation/Slab 3/29/2024 Partial Approval JOSEPH MCGARRY
Pre-Inspection 4/16/2024 Approved ALEJANDRO DE ARTOLA
PLUMBING-Rough 6/18/2024 Partial Approval ALEJANDRO DE ARTOLA
Sewer 6/18/2024 Approved ALEJANDRO DE ARTOLA
Underground Mechanical 6/18/2024 Approved ALEJANDRO DE ARTOLA
Wood Frame 6/18/2024 Corrections Issued ALEJANDRO DE ARTOLA
Insulation 6/27/2024 Partial Approval JOSH MEISTER
Floor/Roof Diaphrgm/Shear Wall 7/1/2024 Partial Approval ALEJANDRO DE ARTOLA
Wood Frame 7/1/2024 Corrections Issued ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 8/15/2024 Partial Approval MICHAEL LEWIS
Deputy Wood Construction 9/13/2024 Conditional Approval ANTHONY RAMOS
Floor/Roof Diaphrgm/Shear Wall 9/13/2024 Partial Approval ANTHONY EGSON
PLUMBING-Rough 9/13/2024 Not Ready for Inspection ANTHONY EGSON
Deputy Wood Construction 9/16/2024 Approved MICHAEL LEWIS
Floor/Roof Diaphrgm/Shear Wall 9/16/2024 Approved MICHAEL LEWIS
ELECTRICAL-Rough 9/17/2024 Corrections Issued MICHAEL LEWIS
PLUMBING-Rough 9/17/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/18/2024 Partial Approval MICHAEL LEWIS
ELECTRICAL-Rough 9/18/2024 Approved MICHAEL LEWIS
Green Building Rough 9/18/2024 Corrections Issued MICHAEL LEWIS
HVAC-Rough 9/18/2024 Approved MICHAEL LEWIS
Verify Sprinkler Sign Off 9/18/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 9/24/2024 Approved ALEJANDRO DE ARTOLA
Green Building Rough 9/24/2024 Approved ALEJANDRO DE ARTOLA
Insulation 9/24/2024 Approved ALEJANDRO DE ARTOLA
Drywall Nailing 9/30/2024 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 9/30/2024 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 10/11/2024 Approved JOAQUIN GREENOUGH
Shower Pan 10/11/2024 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 1/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 1/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Footing/Foundation/Slab 1/13/2025 Approved ALEJANDRO DE ARTOLA
Gas Test 1/13/2025 Approved ALEJANDRO DE ARTOLA
Green Building Final 1/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
HVAC-Final 1/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
PLUMBING-Final 1/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Service/Power Release 1/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Smoke Detectors 1/13/2025 Corrections Issued ALEJANDRO DE ARTOLA
Final 2/4/2025 Permit Finaled ALEJANDRO DE ARTOLA
Green Building Final 2/4/2025 Approved ALEJANDRO DE ARTOLA
Service/Power Release 2/4/2025 Approved ALEJANDRO DE ARTOLA
Smoke Detectors 2/4/2025 Approved ALEJANDRO DE ARTOLA