1079-1081 N MORAGA DR 90049

Certificate Information: 1079-1081 N MORAGA DR 90049

Application / Permit
21014-20001-02669
Plan Check / Job No.
B22VN03123
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (N) ACCESSORY DWELLING UNIT PER LAMC 12.22A33(c)(e) OVER 1ST FLOOR OF (E) 1-STORY SFD W/ ATTACHED GARAGE (NFPA-13D FIRE SPRINKLERS THROUGHOUT); INTERIOR CHANGES TO SFD
Permit Issued
Issued on 6/16/2022
Issuing Office
Current Status
Permit Finaled on 4/10/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/1/2022 APPLICANT
Assigned to Plan Check Engineer 3/10/2022 NILOOFAR MEHRAIN
Corrections Issued 3/15/2022 NILOOFAR MEHRAIN
Quality Review Completed 3/17/2022 STEVEN KIM
Building Plans Picked Up 3/18/2022 APPLICANT
Plan Check Approved 6/2/2022 NILOOFAR MEHRAIN
Issued 6/16/2022 APPLICANT
Permit Finaled 4/9/2024 CARLOS MATAMOROS

Permit Application Clearance Information

Address approval Cleared 5/3/2022 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 5/3/2022 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 5/3/2022 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 5/3/2022 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 5/3/2022 CATHERINE ADROVER
BHO/Hillside ordinance Cleared 5/3/2022 CATHERINE ADROVER
Street Frontage Cleared 5/3/2022 CATHERINE ADROVER
Eng Process Fee Ord 176,300 Cleared 5/12/2022 CATHERINE ADROVER
Sewer availability Cleared 5/12/2022 CATHERINE ADROVER
Hydrant and Access approval Cleared 5/16/2022 JOHN CONNEALLY
Roof/Waste drainage to street Cleared 5/16/2022 CATHERINE ADROVER

Contact Information

Contractor Owner-Builder       ,
Engineer Smith,, Melvin Bruce; Lic. No.: GE2673 2165 N MARVEL AVE      SIMI VALLEY, CA 93065
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361

Inspector Information

EVAN COOPER, (310) 914-3861 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 8/9/2022 Partial Approval ANDREW NAVE
Deputy Wood Construction 9/12/2022 Conditional Approval CARLOS MATAMOROS
Floor/Roof Diaphrgm/Shear Wall 9/12/2022 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 9/19/2022 Corrections Issued KEVIN SARGSYAN
ELECTRICAL-Rough 9/21/2022 Partial Approval CARLOS MATAMOROS
PLUMBING-Rough 9/21/2022 Not Ready for Inspection CARLOS MATAMOROS
Gas Test 9/22/2022 Approved CARLOS MATAMOROS
HVAC-Rough 9/22/2022 Approved CARLOS MATAMOROS
PLUMBING-Rough 9/22/2022 Approved CARLOS MATAMOROS
BUILDING-Rough-Frame 10/3/2022 Approved CARLOS MATAMOROS
FLOOD-Proofing Certificate 10/3/2022 Approved CARLOS MATAMOROS
Green Building Rough 10/3/2022 Approved CARLOS MATAMOROS
Verify Sprinkler Sign Off 10/3/2022 Approved CARLOS MATAMOROS
Shower Pan 10/6/2022 Not Ready for Inspection CARLOS MATAMOROS
Shower Pan 10/11/2022 Approved CARLOS MATAMOROS
Drywall Nailing 10/24/2022 Corrections Issued CLAYTON GRAHAM
Drywall Nailing 10/26/2022 No Access for Inspection CARLOS MATAMOROS
Drywall Nailing 11/1/2022 Approved CARLOS MATAMOROS
ELECTRICAL-Final 8/28/2023 Not Ready for Inspection CHRISTOPHER WILSON
HVAC-Final 8/28/2023 Not Ready for Inspection CHRISTOPHER WILSON
ELECTRICAL-Final 8/29/2023 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Final 8/29/2023 Not Ready for Inspection CARLOS MATAMOROS
PLUMBING-Final 8/29/2023 Not Ready for Inspection CARLOS MATAMOROS
ELECTRICAL-Final 9/22/2023 Approved CARLOS MATAMOROS
HVAC-Final 9/22/2023 Approved CARLOS MATAMOROS
Service/Power Release 9/28/2023 Approved MICHAEL PELHAM
PLUMBING-Final 10/10/2023 Approved CARLOS MATAMOROS
Final 4/9/2024 Permit Finaled CARLOS MATAMOROS
Footing/Foundation/Slab 4/9/2024 Approved CARLOS MATAMOROS
Green Building Final 4/9/2024 Approved CARLOS MATAMOROS