10635 N KESTER AVE 91345
Certificate Information: 10635 N KESTER AVE 91345
- Application / Permit
- 21014-20001-02367
- Plan Check / Job No.
- B23VN00264
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- SUPPLEMENTAL PERMIT FOR 21014-20000-02367 TO MAKE CONVERSION ADU TO NEW CONSTRUCTION ADU
- Permit Issued
- Issued on 5/1/2023
- Issuing Office
- Current Status
- Permit Finaled on 10/18/2023
Permit Application Status History
| Submitted | 1/12/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2023 | CARLOS MONTES |
| Corrections Issued | 2/2/2023 | CARLOS MONTES |
| Applicant returned to address corrections | 3/29/2023 | CARLOS MONTES |
| Plan Check Approved | 4/26/2023 | CARLOS MONTES |
| Issued | 5/1/2023 | APPLICANT |
| Permit Finaled | 10/18/2023 | JENNIFER RABUCHIN |
Permit Application Clearance Information
| ZA Case | Cleared | 2/13/2023 | NELSON RODRIGUEZ |
| Sewer availability | Cleared | 2/16/2023 | COLIN LOREDO |
| Eng Process Fee Ord 176,300 | Cleared | 3/9/2023 | COLIN LOREDO |
| Low Impact Development | Cleared | 3/13/2023 | LUIS LUVANO |
| Roof/Waste drainage to street | Cleared | 3/13/2023 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JOHN COLEMAN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
| JENNIFER RABUCHIN, (818) 374-1179 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 5/4/2023 | Corrections Issued | JENNIFER RABUCHIN |
| PLUMBING-Rough | 5/8/2023 | Partial Approval | JENNIFER RABUCHIN |
| Deputy Drilled-In Anchors | 5/11/2023 | Approved | JENNIFER RABUCHIN |
| Footing/Foundation/Slab | 5/15/2023 | Approved | JENNIFER RABUCHIN |
| Deputy Wood Construction | 6/9/2023 | Partial Approval | JENNIFER RABUCHIN |
| BUILDING-Rough-Frame | 10/18/2023 | Approved | JENNIFER RABUCHIN |
| Final | 10/18/2023 | Permit Finaled | JENNIFER RABUCHIN |
| Green Building Final | 10/18/2023 | Approved | JENNIFER RABUCHIN |
| Green Building Rough | 10/18/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Final | 10/18/2023 | Approved | JENNIFER RABUCHIN |
| MERV13>=Rough | 10/18/2023 | Approved | JENNIFER RABUCHIN |
| Service/Power Release | 10/18/2023 | Not Required | JENNIFER RABUCHIN |
| Smoke Detectors | 10/18/2023 | Approved | JENNIFER RABUCHIN |
| Verify Sprinkler Sign Off | 10/18/2023 | Approved | JENNIFER RABUCHIN |