12630 W MIRANDA ST 1-3 91607

Certificate Information: 12630 W MIRANDA ST 1-3 91607

Application / Permit
21014-20001-01705
Plan Check / Job No.
B21VN10240
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL TO 21014-20000-01705 TO ADD 564 SQ. FT. TO THE (E) SINGLE FAMILY DWELLING.
Permit Issued
Issued on 11/9/2021
Issuing Office
Current Status
Permit Finaled on 4/12/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 8/2/2021 APPLICANT
Assigned to Plan Check Engineer 8/2/2021 COLIN LOREDO
Corrections Issued 8/2/2021 COLIN LOREDO
Plan Check Approved 11/9/2021 COLIN LOREDO
Issued 11/9/2021 APPLICANT
Permit Finaled 4/12/2022 CHRISTOPHE COCHRAN

Permit Application Clearance Information

Low Impact Development Cleared 10/28/2021 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 10/29/2021 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 11/1/2021 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Standley,, Craig Erick; Lic. No.: C87675 5330 ZELZAH AVE UNIT 7      ENCINO, CA 91316

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 11/16/2021 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 11/30/2021 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/30/2021 Not Ready for Inspection CHRISTOPHE COCHRAN
Green Building Rough 11/30/2021 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/7/2021 Partial Approval CHRISTOPHE COCHRAN
Wood Frame 12/7/2021 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 12/15/2021 Partial Approval CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 12/29/2021 Partial Approval CHRISTOPHE COCHRAN
Interior/Exterior Lathing 1/5/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Rough 1/7/2022 Approved CHRISTOPHE COCHRAN
HVAC-Rough 1/7/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Rough 1/7/2022 Approved CHRISTOPHE COCHRAN
Insulation 1/11/2022 Approved CHRISTOPHE COCHRAN
Wood Frame 1/11/2022 Approved CHRISTOPHE COCHRAN
BUILDING-Rough-Frame 4/12/2022 Approved CHRISTOPHE COCHRAN
Drywall Nailing 4/12/2022 Approved CHRISTOPHE COCHRAN
ELECTRICAL-Final 4/12/2022 Approved CHRISTOPHE COCHRAN
Final 4/12/2022 Permit Finaled CHRISTOPHE COCHRAN
Green Building Final 4/12/2022 Approved CHRISTOPHE COCHRAN
HVAC-Final 4/12/2022 Approved CHRISTOPHE COCHRAN
PLUMBING-Final 4/12/2022 Approved CHRISTOPHE COCHRAN
Smoke Detectors 4/12/2022 Approved CHRISTOPHE COCHRAN