3296 S INGLEWOOD BLVD 90066

Certificate Information: 3296 S INGLEWOOD BLVD 90066

Application / Permit
21014-20001-01046
Plan Check / Job No.
B22VN08461
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT TO 21014-20001-01046 TO CONVERT EXISTING GARAGE TO NEW REC ROOM; ADD 3'X 18' PATIO COVER' ADD 18' X 18' IRREGULAR SHAPED CARPORT; ADD 3'-8" X 4'-4" PORCH
Permit Issued
Issued on 8/17/2022
Issuing Office
Valley
Current Status
Permit Finaled on 7/8/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 6/1/2022 APPLICANT
Assigned to Plan Check Engineer 6/1/2022 SELLA BENYAMIN
Corrections Issued 6/1/2022 SELLA BENYAMIN
Plan Check Approved 7/22/2022 SELLA BENYAMIN
Issued 8/17/2022 APPLICANT
Permit Finaled 7/8/2025 ANDREW BEELI

Permit Application Clearance Information

No Data Available.

Contact Information

Architect Di, Zitti, Fernando; Lic. No.: C24587 21243 VENTURA BLVD #115      WOODLAND HILLS, CA 91364
Contractor Baker Mick Construction Inc; Lic. No.: 970371-B 17535 BULLOCK STREET      ENCINO, CA 91316

Inspector Information

ROBERT GARTH, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
JOHN MATTILLO, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PEDRO RIVERA, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
EUSEBIO GUZMAN, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
PAUL REECE, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI
ANDREW BEELI, (213) 978-4498 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Floor/Roof Diaphrgm/Shear Wall 9/21/2022 Partial Approval MARIAN PODPORA
BUILDING-Rough-Frame 10/18/2022 Partial Approval MARIAN PODPORA
Green Building Rough 10/18/2022 Approved MARIAN PODPORA
Interior/Exterior Lathing 10/26/2022 Not Ready for Inspection RYAN BARNES
Insulation 10/31/2022 Approved RYAN BARNES
Drywall Nailing 11/7/2022 Approved JOHN MATTILLO
Deck 5/19/2023 Partial Approval ANDREW BEELI
BUILDING-Rough-Frame 7/8/2025 Approved ANDREW BEELI
ELECTRICAL-Final 7/8/2025 Approved ANDREW BEELI
Final 7/8/2025 Permit Finaled ANDREW BEELI
Footing/Foundation/Slab 7/8/2025 Approved ANDREW BEELI
Green Building Final 7/8/2025 Approved ANDREW BEELI
PLUMBING-Final 7/8/2025 Approved ANDREW BEELI
Rough-Elec/Plmb/HVAC 7/8/2025 Approved ANDREW BEELI
Smoke Detectors 7/8/2025 Approved ANDREW BEELI