7512 W 80TH ST 90045
Certificate Information: 7512 W 80TH ST 90045
- Application / Permit
- 21014-20001-00269
- Plan Check / Job No.
- B21VN15229
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL TO 21014-20000-00269 TO REVISE WORK DESCRIPTION TO STATE NEW 2-STORY 49'-2" X 39'-0" IRREGULAR SHAPED SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING. ORIGINAL WORK DESCRIPTION: "1ST AND 2ND STORY ADDITION TO (E) 1-STORY, IRREGULAR SHAPED SINGLE FAMILY DWELLING WITH ATTACHED GARAGE. NFPA 13D FIRE SPRINKLERS REQUIRED THROUGHOUT. ALL WORK PER ENGINEERING."
- Permit Issued
- Issued on 1/7/2022
- Issuing Office
- Current Status
- Permit Finaled on 9/20/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | COLIN LOREDO |
| Corrections Issued | 11/22/2021 | COLIN LOREDO |
| Quality Review Completed | 11/22/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| Applicant returned to address corrections | 12/8/2021 | COLIN LOREDO |
| Plan Check Approved | 12/16/2021 | COLIN LOREDO |
| Issued | 1/7/2022 | APPLICANT |
| Permit Finaled | 9/19/2022 | BOBBY KEY |
Permit Application Clearance Information
| Address approval | Cleared | 12/7/2021 | NIKTA MOUSAVI |
| Eng Process Fee Ord 176,300 | Cleared | 12/9/2021 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Local Construction Remodeling; Lic. No.: 966738-B | 14901 TUBA STREET MISSION HILLS, CA 91345 |
| Engineer | Motavvef,, Nasser; Lic. No.: C40977 | 15335 MORRISON ST 370 SHERMAN OAKS, CA 91403 |
Inspector Information
| MICHAEL LEWIS, (310) 914-3979 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 9/19/2022 | Approved | BOBBY KEY |
| Drywall Nailing | 9/19/2022 | Approved | BOBBY KEY |
| Final | 9/19/2022 | Permit Finaled | BOBBY KEY |
| Footing/Foundation/Slab | 9/19/2022 | Approved | BOBBY KEY |
| Green Building Final | 9/19/2022 | Approved | BOBBY KEY |
| Green Building Rough | 9/19/2022 | Approved | BOBBY KEY |
| METHANE-Barrier | 9/19/2022 | Approved | BOBBY KEY |
| METHANE-Final | 9/19/2022 | Approved | BOBBY KEY |
| METHANE-Rough | 9/19/2022 | Approved | BOBBY KEY |
| METHANE-Subgrade | 9/19/2022 | Approved | BOBBY KEY |
| Smoke Detectors | 9/19/2022 | Approved | BOBBY KEY |
| Verify Sprinkler Sign Off | 9/19/2022 | Approved | BOBBY KEY |