12832 W HALKIRK ST 91604

Certificate Information: 12832 W HALKIRK ST 91604

Application / Permit
21014-20001-00218
Plan Check / Job No.
B23VN06396
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
SUPPLEMENTAL PERMIT FOR 21014-20000-00218 TO INCREASE ADDITION (19'-8" X 2'-2 1/2", 43.39SF) AT REAR, REDESIGN ROOF FOR VAULTED CEILING, RE-DESIGN ROOF OF FRONT PORCH, EXPAND FRONT PORCH TO (10'-6" X 10'-5") & REVISE/ADD WINDOWS
Permit Issued
Issued on 6/20/2023
Issuing Office
Current Status
Permit Finaled on 8/21/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 5/16/2023 APPLICANT
Assigned to Plan Check Engineer 5/16/2023 NILOOFAR MEHRAIN
Corrections Issued 5/16/2023 NILOOFAR MEHRAIN
Plan Check Approved 6/1/2023 NILOOFAR MEHRAIN
Building Plans Picked Up 6/14/2023 APPLICANT
Issued 6/20/2023 APPLICANT
Permit Finaled 8/21/2025 CHRISTOPHE COCHRAN

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 5/23/2023 CARLOS AGUILERA
Low Impact Development (LID) Cleared 6/2/2023 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 6/12/2023 MEGAN GODINEZ

Contact Information

Contractor Jarh Builders Corporation; Lic. No.: 1074687-B 15740 PARAMOUNT BLVD #E      PARAMOUNT, CA 90723
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364

Inspector Information

CHRISTOPHE COCHRAN, (818) 374-1165 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 8/18/2023 Corrections Issued JUAN VALENZUELA
Deputy Drilled-In Anchors 8/21/2023 Conditional Approval ROBERT GOLD
Footing/Foundation/Slab 8/23/2023 Not Ready for Inspection CHRISTOPHE COCHRAN
Footing/Foundation/Slab 8/28/2023 Approved CHRISTOPHE COCHRAN
Pre-Inspection 10/10/2023 Approved CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 11/13/2023 Partial Approval CHRISTOPHE COCHRAN
Floor/Roof Diaphrgm/Shear Wall 4/1/2024 Approved JOHN COLEMAN
Interior/Exterior Lathing 4/1/2024 Partial Approval JOHN COLEMAN
Insulation 4/10/2024 Conditional Approval CHRISTOPHE COCHRAN
Drywall Nailing 4/30/2024 Approved CHRISTOPHE COCHRAN
Insulation 4/30/2024 Approved CHRISTOPHE COCHRAN
Interior/Exterior Lathing 6/5/2024 Partial Approval CHRISTOPHE COCHRAN
Final 8/21/2025 Permit Finaled CHRISTOPHE COCHRAN
Green Building Final 8/21/2025 Approved CHRISTOPHE COCHRAN
Green Building Rough 8/21/2025 Approved CHRISTOPHE COCHRAN
Verify Sprinkler Sign Off 8/21/2025 Approved CHRISTOPHE COCHRAN
Wood Frame 8/21/2025 Approved CHRISTOPHE COCHRAN