12832 W HALKIRK ST 91604
Certificate Information: 12832 W HALKIRK ST 91604
- Application / Permit
- 21014-20001-00218
- Plan Check / Job No.
- B23VN06396
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- SUPPLEMENTAL PERMIT FOR 21014-20000-00218 TO INCREASE ADDITION (19'-8" X 2'-2 1/2", 43.39SF) AT REAR, REDESIGN ROOF FOR VAULTED CEILING, RE-DESIGN ROOF OF FRONT PORCH, EXPAND FRONT PORCH TO (10'-6" X 10'-5") & REVISE/ADD WINDOWS
- Permit Issued
- Issued on 6/20/2023
- Issuing Office
- Current Status
- Permit Finaled on 8/21/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 5/16/2023 | APPLICANT |
| Assigned to Plan Check Engineer | 5/16/2023 | NILOOFAR MEHRAIN |
| Corrections Issued | 5/16/2023 | NILOOFAR MEHRAIN |
| Plan Check Approved | 6/1/2023 | NILOOFAR MEHRAIN |
| Building Plans Picked Up | 6/14/2023 | APPLICANT |
| Issued | 6/20/2023 | APPLICANT |
| Permit Finaled | 8/21/2025 | CHRISTOPHE COCHRAN |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 5/23/2023 | CARLOS AGUILERA |
| Low Impact Development (LID) | Cleared | 6/2/2023 | ANTHONY VARGAS |
| Roof/Waste drainage to street | Cleared | 6/12/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Jarh Builders Corporation; Lic. No.: 1074687-B | 15740 PARAMOUNT BLVD #E PARAMOUNT, CA 90723 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| CHRISTOPHE COCHRAN, (818) 374-1165 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 8/18/2023 | Corrections Issued | JUAN VALENZUELA |
| Deputy Drilled-In Anchors | 8/21/2023 | Conditional Approval | ROBERT GOLD |
| Footing/Foundation/Slab | 8/23/2023 | Not Ready for Inspection | CHRISTOPHE COCHRAN |
| Footing/Foundation/Slab | 8/28/2023 | Approved | CHRISTOPHE COCHRAN |
| Pre-Inspection | 10/10/2023 | Approved | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 11/13/2023 | Partial Approval | CHRISTOPHE COCHRAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/1/2024 | Approved | JOHN COLEMAN |
| Interior/Exterior Lathing | 4/1/2024 | Partial Approval | JOHN COLEMAN |
| Insulation | 4/10/2024 | Conditional Approval | CHRISTOPHE COCHRAN |
| Drywall Nailing | 4/30/2024 | Approved | CHRISTOPHE COCHRAN |
| Insulation | 4/30/2024 | Approved | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 6/5/2024 | Partial Approval | CHRISTOPHE COCHRAN |
| Final | 8/21/2025 | Permit Finaled | CHRISTOPHE COCHRAN |
| Green Building Final | 8/21/2025 | Approved | CHRISTOPHE COCHRAN |
| Green Building Rough | 8/21/2025 | Approved | CHRISTOPHE COCHRAN |
| Verify Sprinkler Sign Off | 8/21/2025 | Approved | CHRISTOPHE COCHRAN |
| Wood Frame | 8/21/2025 | Approved | CHRISTOPHE COCHRAN |