3459 N ARDSLEY PL 91436
Certificate Information: 3459 N ARDSLEY PL 91436
- Application / Permit
- 21014-20000-06429
- Plan Check / Job No.
- B21VN17996
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 6'-3" X 14'-7.5" ADDITION AND REMODEL FOR NEW WINDOWS AT BEDROOMS, BATHROOM, LIVING ROOM, DINING ROOM, AND KITCHEN. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 4/5/2022
- Issuing Office
- Current Status
- CofO Issued on 2/16/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2022 | RAPHAEL ROSAS |
| Corrections Issued | 1/8/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 3/29/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Issued | 4/5/2022 | APPLICANT |
| CofO in Progress | 2/16/2023 | VINCENT HANLEY |
| CofO Issued | 2/16/2023 | MICHAEL SMITH |
| Permit Finaled | 2/16/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Grading Pre-Inspection | Cleared | 1/24/2022 | MANUEL TEJADA |
| Roof/Waste drainage to street | Cleared | 1/25/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | CARLOS AGUILERA |
| Specific Plan | Cleared | 3/10/2022 | OLGA AYALA |
| Specific Plan | Cleared | 3/10/2022 | OLGA AYALA |
| ZI | Cleared | 3/10/2022 | OLGA AYALA |
| ZI | Cleared | 3/10/2022 | OLGA AYALA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Shakiban,, George; Lic. No.: C39908 | 23945 CALABASAS RD STE 101 CALABASAS, CA 91302 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/18/2022 | Corrections Issued | DAVID SANDOVAL |
| BUILDING-Rough-Frame | 9/15/2022 | Approved | VINCENT HANLEY |
| ELECTRICAL-Rough | 9/15/2022 | Approved | VINCENT HANLEY |
| Green Building Rough | 9/15/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 9/15/2022 | Approved | VINCENT HANLEY |
| PLUMBING-Rough | 9/15/2022 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 10/4/2022 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Final | 2/1/2023 | Approved | VINCENT HANLEY |
| Final | 2/1/2023 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/1/2023 | Approved | VINCENT HANLEY |
| Green Building Final | 2/1/2023 | Approved | VINCENT HANLEY |
| PLUMBING-Final | 2/1/2023 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/1/2023 | SGSOV Approved | VINCENT HANLEY |
| Smoke Detectors | 2/1/2023 | Approved | VINCENT HANLEY |
| Final | 2/16/2023 | OK to Issue CofO | VINCENT HANLEY |