6653 N AMIGO AVE 91335
Certificate Information: 6653 N AMIGO AVE 91335
- Application / Permit
- 21014-20000-06388
- Plan Check / Job No.
- B21VN17873
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 36' X 13'-6" ADDITION AND INTERIOR REMODEL TO (E) SFD.
- Permit Issued
- Issued on 6/14/2022
- Issuing Office
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/7/2022 | SERGIO MUNIZ |
| Corrections Issued | 1/9/2022 | SERGIO MUNIZ |
| Plan Check Approved | 5/20/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 5/24/2022 | APPLICANT |
| Issued | 6/14/2022 | APPLICANT |
| CofO in Progress | 10/19/2023 | JEFFREY BULL |
| Permit Finaled | 12/5/2023 | JOHN JANSON |
| CofO Issued | 12/5/2023 | JOHN JANSON |
| Permit Finaled | 12/5/2023 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2022 | DAGOVERTO GUERRERO |
| Sewer availability | Cleared | 2/8/2022 | DAGOVERTO GUERRERO |
| Low Impact Development | Cleared | 4/20/2022 | JORGE MEJIA LEMUS |
| Roof/Waste drainage to street | Cleared | 5/3/2022 | DAGOVERTO GUERRERO |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| ARUTYUN MADATYAN, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
| JUAN ALVARADO, (818) 774-4307 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 8/1/2022 | Approved | JEFFREY BULL |
| Footing/Foundation/Slab | 8/5/2022 | Approved | JEFFREY BULL |
| Insulation | 8/12/2022 | Partial Inspection | JUSTIN HAWLEY |
| PLUMBING-Rough | 8/12/2022 | Corrections Issued | JUSTIN HAWLEY |
| Insulation | 8/18/2022 | Partial Approval | JEFFREY BULL |
| PLUMBING-Rough | 8/18/2022 | Partial Approval | JEFFREY BULL |
| Floor/Roof Diaphrgm/Shear Wall | 9/6/2022 | Approved | JEFFREY BULL |
| Wood Frame | 9/6/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 9/16/2022 | Not Ready for Inspection | JEFFREY BULL |
| Interior/Exterior Lathing | 9/16/2022 | Not Ready for Inspection | JEFFREY BULL |
| PLUMBING-Rough | 9/16/2022 | Not Ready for Inspection | JEFFREY BULL |
| Sewer | 9/16/2022 | Approved | JEFFREY BULL |
| ELECTRICAL-Rough | 9/20/2022 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 9/20/2022 | Partial Approval | JEFFREY BULL |
| HVAC-Rough | 9/30/2022 | Approved | JEFFREY BULL |
| BUILDING-Rough-Frame | 10/6/2022 | Approved | SEAN HAUPT |
| Green Building Rough | 10/6/2022 | Approved | SEAN HAUPT |
| Insulation | 10/6/2022 | Approved | SEAN HAUPT |
| Drywall Nailing | 10/17/2022 | Approved | KRISTEN CAUSEY |
| Grounding or Bonding | 11/23/2022 | Not Ready for Inspection | JEFFREY BULL |
| Interior/Exterior Lathing | 11/23/2022 | Not Ready for Inspection | JEFFREY BULL |
| Rough-Elec/Plmb/HVAC | 11/23/2022 | Approved | JEFFREY BULL |
| Sewer | 11/23/2022 | Approved | JEFFREY BULL |
| Shower Pan | 11/23/2022 | Approved | JEFFREY BULL |
| Interior/Exterior Lathing | 12/2/2022 | Approved | MORRIS JACKSON |
| ELECTRICAL-Final | 12/8/2022 | Not Ready for Inspection | JEFFREY BULL |
| Grounding or Bonding | 12/8/2022 | Not Ready for Inspection | JEFFREY BULL |
| Rough-Elec/Plmb/HVAC | 12/8/2022 | Approved | JEFFREY BULL |
| Smoke Detectors | 12/8/2022 | Not Ready for Inspection | JEFFREY BULL |
| ELECTRICAL-Final | 3/23/2023 | Corrections Issued | CHRIS CHRISTENSEN |
| ELECTRICAL-Final | 5/9/2023 | Approved | SEAN WIRCH |
| ELECTRICAL-Final | 8/18/2023 | Approved | JEFFREY BULL |
| Final | 8/18/2023 | Corrections Issued | JEFFREY BULL |
| Green Building Final | 8/18/2023 | Not Ready for Inspection | JEFFREY BULL |
| Grounding or Bonding | 8/18/2023 | Approved | JEFFREY BULL |
| SGSOV-Seismic Gas S/O Valve | 8/18/2023 | SGSOV Approved | JEFFREY BULL |
| Service/Power Release | 8/18/2023 | Approved | JEFFREY BULL |
| Smoke Detectors | 8/18/2023 | Approved | JEFFREY BULL |
| Final | 10/19/2023 | OK to Issue CofO | JEFFREY BULL |
| Green Building Final | 10/19/2023 | Approved | JEFFREY BULL |