3019 S POTOMAC AVE 90016
Certificate Information: 3019 S POTOMAC AVE 90016
- Application / Permit
- 21014-20000-06383
- Plan Check / Job No.
- B21VN17870
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 20' X 14'-6" ADDITION AND REMODEL TO (E) DWELLING TO ADD TWO NEW BATHROOMS AND REARRANGE FLOOR PLAN LAYOUT.
- Permit Issued
- Issued on 6/8/2022
- Issuing Office
- Current Status
- CofO Issued on 9/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/30/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 12/31/2021 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 2/8/2022 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 4/8/2022 | RARES BODEA |
| Applicant returned to address corrections | 5/26/2022 | JEROME MAGAT PALMA |
| Applicant returned to address corrections | 6/7/2022 | JEROME MAGAT PALMA |
| Issued | 6/8/2022 | APPLICANT |
| Building Plans Picked Up | 6/8/2022 | APPLICANT |
| CofO in Progress | 9/13/2023 | CALEB MEISTER |
| Permit Finaled | 9/13/2023 | DEROLD HAUFF |
| CofO Issued | 9/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 2/1/2022 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 2/2/2022 | ABEL CASILLAS |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/15/2022 | Partial Approval | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 6/15/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/22/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 6/22/2022 | Partial Approval | STUART CHAPMAN |
| FLOOD-Proofing Certificate | 6/22/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 6/22/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 6/22/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 6/22/2022 | Approved | STUART CHAPMAN |
| Wood Frame | 6/22/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 6/28/2022 | Partial Approval | RYAN SALAZAR |
| Shower Pan | 6/28/2022 | Not Ready for Inspection | RYAN SALAZAR |
| Shower Pan | 6/30/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 7/7/2022 | Partial Approval | STUART CHAPMAN |
| Interior/Exterior Lathing | 7/14/2022 | Partial Approval | STUART CHAPMAN |
| Pre-Inspection | 7/14/2022 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 7/21/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 7/25/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 8/1/2022 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 8/4/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 8/4/2022 | Not Ready for Inspection | STUART CHAPMAN |
| HVAC-Rough | 8/4/2022 | Not Ready for Inspection | STUART CHAPMAN |
| BUILDING-Rough-Frame | 9/13/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 9/13/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 9/13/2022 | Approved | STUART CHAPMAN |
| Insulation | 9/13/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 9/13/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 9/13/2022 | Approved | STUART CHAPMAN |
| Sewer | 9/13/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Insulation | 9/15/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 9/15/2022 | Partial Approval | STUART CHAPMAN |
| PLUMBING-Rough | 9/15/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 9/28/2022 | Approved | STUART CHAPMAN |
| ELECTRICAL-Rough | 9/28/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Rough | 9/28/2022 | Approved | STUART CHAPMAN |
| Wood Frame | 9/28/2022 | Approved | STUART CHAPMAN |
| Final | 6/15/2023 | Corrections Issued | STUART CHAPMAN |
| Footing/Foundation/Slab | 6/15/2023 | Approved | STUART CHAPMAN |
| Green Building Final | 6/15/2023 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 6/15/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Smoke Detectors | 6/15/2023 | Approved | STUART CHAPMAN |
| ELECTRICAL-Final | 6/20/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Final | 6/20/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Final | 6/20/2023 | Not Ready for Inspection | CALEB MEISTER |
| ELECTRICAL-Final | 6/21/2023 | Not Ready for Inspection | CALEB MEISTER |
| HVAC-Final | 6/21/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Final | 6/21/2023 | Not Ready for Inspection | CALEB MEISTER |
| Final | 9/13/2023 | OK to Issue CofO | CALEB MEISTER |
| SGSOV-Seismic Gas S/O Valve | 9/13/2023 | SGSOV Approved | CALEB MEISTER |