13373 W BEAVER ST 91342
Certificate Information: 13373 W BEAVER ST 91342
- Application / Permit
- 21014-20000-06377
- Plan Check / Job No.
- B21VN17851
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADD TO & CONVERT GARAGE TO ACCESSORY DWELLING UNIT per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 3/23/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/31/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 2/4/2022 | MOHAMMAD ESMAILI |
| Corrections Issued | 2/10/2022 | MOHAMMAD ESMAILI |
| Quality Review Completed | 2/18/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 3/16/2022 | APPLICANT |
| Applicant returned to address corrections | 2/6/2023 | MOHAMMAD ESMAILI |
| Plan Check Approved | 3/23/2023 | MOHAMMAD ESMAILI |
| Issued | 3/23/2023 | APPLICANT |
| CofO in Progress | 4/15/2024 | KEVIN BERBERYAN |
| Permit Finaled | 4/18/2024 | RUBEN SALAS |
| CofO Issued | 4/18/2024 | RUBEN SALAS |
| Permit Finaled | 4/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 8/24/2022 | MEGAN GODINEZ |
| Construction near power lines | Cleared | 8/26/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 8/29/2022 | MEGAN GODINEZ |
| Sewer availability | Cleared | 8/29/2022 | MEGAN GODINEZ |
| Low Impact Development | Cleared | 1/6/2023 | ROGELIO CORTES |
| Roof/Waste drainage to street | Cleared | 1/17/2023 | MEGAN GODINEZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/28/2023 | Partial Inspection | ARAM AVEDISIAN |
| PLUMBING-Rough | 6/6/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 7/5/2023 | Approved | MICHEL ABAJAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/26/2023 | Partial Approval | MISAEL ESPARZA |
| Green Building Rough | 7/26/2023 | Not Ready for Inspection | MISAEL ESPARZA |
| Floor/Roof Diaphrgm/Shear Wall | 8/17/2023 | Partial Approval | ROBERT GOLD |
| BUILDING-Rough-Frame | 10/4/2023 | Conditional Approval | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/4/2023 | Corrections Issued | KEVIN BERBERYAN |
| HVAC-Rough | 10/4/2023 | Corrections Issued | KEVIN BERBERYAN |
| PLUMBING-Rough | 10/4/2023 | Approved | KEVIN BERBERYAN |
| ELECTRICAL-Rough | 10/10/2023 | Approved | KEVIN BERBERYAN |
| HVAC-Rough | 10/10/2023 | Approved | KEVIN BERBERYAN |
| Interior/Exterior Lathing | 10/10/2023 | Approved | KEVIN BERBERYAN |
| BUILDING-Rough-Frame | 10/23/2023 | Approved | KEVIN BERBERYAN |
| Green Building Rough | 10/23/2023 | Approved | KEVIN BERBERYAN |
| Insulation | 11/20/2023 | Approved | KEVIN BERBERYAN |
| Drywall Nailing | 12/29/2023 | Approved | MICHEL ABAJAN |
| Interior/Exterior Lathing | 12/29/2023 | Approved | MICHEL ABAJAN |
| Shower Pan | 12/29/2023 | Approved | MICHEL ABAJAN |
| Final | 4/4/2024 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 4/4/2024 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 4/4/2024 | SGSOV Approved | DAVID ANDERSON |
| Smoke Detectors | 4/4/2024 | Not Ready for Inspection | DAVID ANDERSON |
| Final | 4/11/2024 | Corrections Issued | KEVIN BERBERYAN |
| Smoke Detectors | 4/11/2024 | Approved | KEVIN BERBERYAN |
| Final | 4/12/2024 | OK to Issue CofO | KEVIN BERBERYAN |