7654 S AIRPORT BLVD 90045

Certificate Information: 7654 S AIRPORT BLVD 90045

Application / Permit
21014-20000-06369
Plan Check / Job No.
B21VN17835
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADDITION OF A SECOND FLOOR TO (E) 1 STORY HOUSE, KITCHEN REMODELING
Permit Issued
Issued on 6/24/2022
Issuing Office
Current Status
CofO Issued on 1/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2021 APPLICANT
Assigned to Plan Check Engineer 2/3/2022 SUNMIN LEE
Corrections Issued 2/8/2022 SUNMIN LEE
Quality Review Completed 2/18/2022 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 4/22/2022 SUNMIN LEE
Building Plans Picked Up 4/25/2022 APPLICANT
Applicant returned to address corrections 6/8/2022 SUNMIN LEE
Plan Check Approved 6/14/2022 SUNMIN LEE
Issued 6/24/2022 APPLICANT
CofO in Progress 12/20/2022 BOBBY KEY
Permit Finaled 1/7/2023 DANIEL ORRANTE
CofO Issued 1/7/2023 DANIEL ORRANTE
Permit Finaled 1/7/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 3/10/2022 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 3/13/2022 DENNIS BRAGIN
Sewer availability Cleared 3/13/2022 DENNIS BRAGIN
Grading Pre-Inspection Cleared 4/22/2022 SUNMIN LEE

Contact Information

Contractor Eden Development & Consulting Inc; Lic. No.: 984612-B 13455 VENTURA BLVD STE 215      SHERMAN OAKS, CA 91423
Engineer Barakat,, Fouad Chafic; Lic. No.: C67449 11 CEDARWOOD DR      POMONA, CA 91766

Inspector Information

MICHAEL LEWIS, (310) 914-3979 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 7/5/2022 Corrections Issued STEPHANIE SWANSON
Floor/Roof Diaphrgm/Shear Wall 7/18/2022 Partial Approval HERBERT GIRON
BUILDING-Rough-Frame 8/31/2022 Partial Approval BOBBY KEY
ELECTRICAL-Rough 8/31/2022 Approved BOBBY KEY
Green Building Rough 8/31/2022 Approved BOBBY KEY
HVAC-Rough 8/31/2022 Corrections Issued BOBBY KEY
PLUMBING-Rough 8/31/2022 Approved BOBBY KEY
BUILDING-Rough-Frame 9/9/2022 Approved BOBBY KEY
Final 9/9/2022 Corrections Issued BOBBY KEY
HVAC-Rough 9/9/2022 Approved BOBBY KEY
Insulation 9/9/2022 Approved BOBBY KEY
Interior/Exterior Lathing 9/9/2022 Approved BOBBY KEY
Shower Pan 9/9/2022 Approved BOBBY KEY
Drywall Nailing 9/19/2022 Approved BOBBY KEY
Final 11/28/2022 Corrections Issued BOBBY KEY
Footing/Foundation/Slab 11/28/2022 Approved BOBBY KEY
Green Building Final 11/28/2022 Approved BOBBY KEY
SGSOV-Seismic Gas S/O Valve 11/28/2022 SGSOV Approved BOBBY KEY
Smoke Detectors 11/28/2022 Approved BOBBY KEY
ELECTRICAL-Final 12/20/2022 Approved BOBBY KEY
Final 12/20/2022 OK to Issue CofO BOBBY KEY
HVAC-Final 12/20/2022 Approved BOBBY KEY
PLUMBING-Final 12/20/2022 Approved BOBBY KEY