3944 W EDENHURST AVE 90039

Certificate Information: 3944 W EDENHURST AVE 90039

Application / Permit
21014-20000-06368
Plan Check / Job No.
B21VN17834
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
26' X 16' ADDITION OF ONE NEW BEDROOM AND TWO NEW BATHROOMS TO (E) SFD.
Permit Issued
Issued on 3/14/2022
Issuing Office
Current Status
CofO Issued on 10/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/27/2021 APPLICANT
Assigned to Plan Check Engineer 1/7/2022 SERGIO MUNIZ
Corrections Issued 1/9/2022 SERGIO MUNIZ
Plan Check Approved 2/23/2022 SERGIO MUNIZ
Building Plans Picked Up 3/8/2022 APPLICANT
Issued 3/14/2022 APPLICANT
CofO in Progress 8/24/2023 HAMIK HARTOUNIAN
Permit Finaled 10/3/2023 DEROLD HAUFF
CofO Issued 10/3/2023 DEROLD HAUFF
Permit Finaled 10/3/2023 DEROLD HAUFF

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/27/2022 STEVE MELGAR
Sewer availability Cleared 2/8/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 2/9/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,
Engineer Boranian,, Paul Darian; Lic. No.: S5944 23261 BURBANK BL      WOODLAND HILLS, CA 91367

Inspector Information

NICHOLAS LOPEZ, (213) 202-3224 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 8/31/2022 Conditional Approval HAMIK HARTOUNIAN
Deputy Wood Construction 8/31/2022 Conditional Approval HAMIK HARTOUNIAN
Pre-Inspection 9/7/2022 Partial Inspection HAMIK HARTOUNIAN
Excavation/Setback/Form/Re-Bar 9/21/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 10/3/2022 Partial Approval HAMIK HARTOUNIAN
Insulation 10/3/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/6/2022 Partial Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/14/2022 Corrections Issued HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 10/26/2022 Corrections Issued HAMIK HARTOUNIAN
Deputy Wood Construction 10/27/2022 Conditional Approval HAMIK HARTOUNIAN
Floor/Roof Diaphrgm/Shear Wall 11/8/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 11/8/2022 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Rough 11/17/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 11/17/2022 Partial Approval HAMIK HARTOUNIAN
PLUMBING-Rough 11/17/2022 Approved HAMIK HARTOUNIAN
BUILDING-Rough-Frame 12/1/2022 Partial Approval JOSEPH MCGARRY
Green Building Rough 12/1/2022 Partial Approval JOSEPH MCGARRY
HVAC-Rough 12/1/2022 Not Ready for Inspection JOSEPH MCGARRY
BUILDING-Rough-Frame 12/7/2022 Approved HAMIK HARTOUNIAN
Green Building Rough 12/7/2022 Approved HAMIK HARTOUNIAN
Insulation 12/7/2022 Partial Approval HAMIK HARTOUNIAN
Drywall Nailing 12/15/2022 Approved HAMIK HARTOUNIAN
Insulation 12/15/2022 Approved HAMIK HARTOUNIAN
Interior/Exterior Lathing 12/30/2022 Approved HAMIK HARTOUNIAN
Shower Pan 12/30/2022 Conditional Approval HAMIK HARTOUNIAN
Final 8/11/2023 Corrections Issued HAMIK HARTOUNIAN
Footing/Foundation/Slab 8/11/2023 Approved HAMIK HARTOUNIAN
Green Building Final 8/11/2023 Approved HAMIK HARTOUNIAN
PLUMBING-Final 8/11/2023 Approved HAMIK HARTOUNIAN
SGSOV-Seismic Gas S/O Valve 8/11/2023 SGSOV Approved HAMIK HARTOUNIAN
Smoke Detectors 8/11/2023 Approved HAMIK HARTOUNIAN
Final 8/24/2023 OK to Issue CofO HAMIK HARTOUNIAN