8011 N GLENCREST DR 91352

Certificate Information: 8011 N GLENCREST DR 91352

Application / Permit
21014-20000-06350
Plan Check / Job No.
B21VN17744
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
15' X 22'9" ADITION TO THE (E) SINGLE FAMILY DWELLING TO ADD MASTER BEDROOM AND BATHROOM.
Permit Issued
Issued on 4/25/2022
Issuing Office
Current Status
Issued on 4/25/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/22/2021 APPLICANT
Assigned to Plan Check Engineer 12/23/2021 SERGIO MUNIZ
Corrections Issued 12/23/2021 SERGIO MUNIZ
Applicant returned to address corrections 3/22/2022 SERGIO MUNIZ
Plan Check Approved 4/6/2022 SERGIO MUNIZ
Building Plans Picked Up 4/15/2022 APPLICANT
Issued 4/25/2022 APPLICANT

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/18/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 1/19/2022 JOSE DUARTE-DIAZ
ZA Case Cleared 1/19/2022 LAUREN PADICK
Hydrant and Access approval Cleared 3/11/2022 MATTHEW CRAIG
Grading Pre-Inspection Cleared 3/22/2022 SERGIO MUNIZ

Contact Information

Architect Gilliam,, Jonathan; Lic. No.: C33995 15017 ARCHWOOD STREET      VAN NUYS, CA 91405
Contractor C B C Inc; Lic. No.: 868603-B P O BOX 8273      LA CRESCENTA, CA 91224

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/12/2022 Approved CHRISTOPHER DELLEFIELD
PLUMBING-Rough 5/26/2022 Partial Approval WILLIAM WREN
BUILDING-Rough-Frame 6/1/2022 Partial Approval CHRISTOPHER DELLEFIELD
Green Building Rough 6/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
MERV13>=Rough 6/1/2022 Not Ready for Inspection CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 6/6/2022 Approved CHRISTOPHER DELLEFIELD
BUILDING-Rough-Frame 6/27/2022 Partial Approval DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 6/27/2022 Approved DAVID ANDERSON
Green Building Rough 6/27/2022 Partial Approval DAVID ANDERSON
MERV13>=Rough 6/27/2022 Not Ready for Inspection DAVID ANDERSON
ELECTRICAL-Rough 7/8/2022 Approved DAVID ANDERSON
HVAC-Rough 7/8/2022 Approved DAVID ANDERSON
PLUMBING-Rough 7/8/2022 Approved DAVID ANDERSON
Insulation 7/18/2022 Approved DAVID ANDERSON
Shower Pan 7/18/2022 Approved DAVID ANDERSON
Drywall Nailing 7/26/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 7/26/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 8/15/2022 Approved DAVID ANDERSON
ELECTRICAL-Final 9/26/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 10/6/2022 Approved DAVID ANDERSON
Final 10/6/2022 Corrections Issued DAVID ANDERSON
Green Building Final 10/6/2022 Approved DAVID ANDERSON
Green Building Rough 10/6/2022 Approved DAVID ANDERSON
MERV13>=Final 10/6/2022 Approved DAVID ANDERSON
MERV13>=Rough 10/6/2022 Approved DAVID ANDERSON
PLUMBING-Final 10/6/2022 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/6/2022 SGSOV Not Ready DAVID ANDERSON
Smoke Detectors 10/6/2022 Approved DAVID ANDERSON