8011 N GLENCREST DR 91352
Certificate Information: 8011 N GLENCREST DR 91352
- Application / Permit
- 21014-20000-06350
- Plan Check / Job No.
- B21VN17744
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 15' X 22'9" ADITION TO THE (E) SINGLE FAMILY DWELLING TO ADD MASTER BEDROOM AND BATHROOM.
- Permit Issued
- Issued on 4/25/2022
- Issuing Office
- Current Status
- Issued on 4/25/2022
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 12/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | SERGIO MUNIZ |
| Corrections Issued | 12/23/2021 | SERGIO MUNIZ |
| Applicant returned to address corrections | 3/22/2022 | SERGIO MUNIZ |
| Plan Check Approved | 4/6/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 4/15/2022 | APPLICANT |
| Issued | 4/25/2022 | APPLICANT |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/18/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | JOSE DUARTE-DIAZ |
| ZA Case | Cleared | 1/19/2022 | LAUREN PADICK |
| Hydrant and Access approval | Cleared | 3/11/2022 | MATTHEW CRAIG |
| Grading Pre-Inspection | Cleared | 3/22/2022 | SERGIO MUNIZ |
Contact Information
| Architect | Gilliam,, Jonathan; Lic. No.: C33995 | 15017 ARCHWOOD STREET VAN NUYS, CA 91405 |
| Contractor | C B C Inc; Lic. No.: 868603-B | P O BOX 8273 LA CRESCENTA, CA 91224 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/12/2022 | Approved | CHRISTOPHER DELLEFIELD |
| PLUMBING-Rough | 5/26/2022 | Partial Approval | WILLIAM WREN |
| BUILDING-Rough-Frame | 6/1/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 6/1/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| MERV13>=Rough | 6/1/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 6/27/2022 | Partial Approval | DAVID ANDERSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/27/2022 | Approved | DAVID ANDERSON |
| Green Building Rough | 6/27/2022 | Partial Approval | DAVID ANDERSON |
| MERV13>=Rough | 6/27/2022 | Not Ready for Inspection | DAVID ANDERSON |
| ELECTRICAL-Rough | 7/8/2022 | Approved | DAVID ANDERSON |
| HVAC-Rough | 7/8/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 7/8/2022 | Approved | DAVID ANDERSON |
| Insulation | 7/18/2022 | Approved | DAVID ANDERSON |
| Shower Pan | 7/18/2022 | Approved | DAVID ANDERSON |
| Drywall Nailing | 7/26/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/26/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 8/15/2022 | Approved | DAVID ANDERSON |
| ELECTRICAL-Final | 9/26/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 10/6/2022 | Approved | DAVID ANDERSON |
| Final | 10/6/2022 | Corrections Issued | DAVID ANDERSON |
| Green Building Final | 10/6/2022 | Approved | DAVID ANDERSON |
| Green Building Rough | 10/6/2022 | Approved | DAVID ANDERSON |
| MERV13>=Final | 10/6/2022 | Approved | DAVID ANDERSON |
| MERV13>=Rough | 10/6/2022 | Approved | DAVID ANDERSON |
| PLUMBING-Final | 10/6/2022 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 10/6/2022 | SGSOV Not Ready | DAVID ANDERSON |
| Smoke Detectors | 10/6/2022 | Approved | DAVID ANDERSON |