14403 W MIRANDA ST 91401

Certificate Information: 14403 W MIRANDA ST 91401

Application / Permit
21014-20000-06348
Plan Check / Job No.
B21VN17713
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
16' X 28' ADDITION OF A MASTER BEDROOM AND BATHROOM TO EXISTING SINGLE FAMILY DWELLING AND REMODEL - ALL WORK PER ENGINEER
Permit Issued
Issued on 5/16/2022
Issuing Office
Current Status
CofO Issued on 3/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2021 APPLICANT
Assigned to Plan Check Engineer 12/22/2021 DANIEL ABRAMYAN
Corrections Issued 12/30/2021 DANIEL ABRAMYAN
Applicant returned to address corrections 2/3/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 3/31/2022 DANIEL ABRAMYAN
Applicant returned to address corrections 5/11/2022 DANIEL ABRAMYAN
Plan Check Approved 5/13/2022 DANIEL ABRAMYAN
Issued 5/16/2022 APPLICANT
Building Plans Picked Up 5/18/2022 APPLICANT
CofO in Progress 1/26/2023 RYAN SALAZAR
Permit Finaled 3/2/2023 MICHAEL SMITH
CofO Issued 3/2/2023 MICHAEL SMITH
Permit Finaled 3/2/2023 MICHAEL SMITH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 1/7/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 1/7/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 1/7/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

JOSE AVILA, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI
VINCENT HANLEY, (818) 374-1173 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/25/2022 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/8/2022 Partial Approval RICHARD DOCKUS
PLUMBING-Rough 6/8/2022 Partial Approval RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 6/15/2022 Partial Approval CHRISTOPHER DELLEFIELD
Gas Test 7/5/2022 Approved RICHARD DOCKUS
PLUMBING-Rough 7/5/2022 Approved RICHARD DOCKUS
Wood Frame 7/5/2022 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 7/11/2022 Approved RICHARD DOCKUS
HVAC-Rough 7/11/2022 Approved RICHARD DOCKUS
Wood Frame 7/13/2022 Partial Approval RICHARD DOCKUS
Interior/Exterior Lathing 7/15/2022 Not Ready for Inspection RICHARD DOCKUS
Insulation 7/19/2022 Approved RICHARD DOCKUS
Drywall Nailing 7/22/2022 Corrections Issued RICHARD DOCKUS
Shower Pan 8/2/2022 Approved RICHARD DOCKUS
Underground Mechanical 8/2/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 8/5/2022 Partial Approval RICHARD DOCKUS
BUILDING-Rough-Frame 8/11/2022 Approved RICHARD DOCKUS
Drywall Nailing 8/11/2022 Approved RICHARD DOCKUS
Green Building Rough 8/11/2022 Approved RICHARD DOCKUS
Interior/Exterior Lathing 8/11/2022 Not Ready for Inspection RICHARD DOCKUS
Interior/Exterior Lathing 8/17/2022 Approved WILLIAM WREN
Sewer 8/17/2022 Approved WILLIAM WREN
ELECTRICAL-Final 1/25/2023 Approved RYAN SALAZAR
Final 1/25/2023 OK to Issue CofO RYAN SALAZAR
Green Building Final 1/25/2023 Approved RYAN SALAZAR
HVAC-Final 1/25/2023 Approved RYAN SALAZAR
PLUMBING-Final 1/25/2023 Approved RYAN SALAZAR
SGSOV-Seismic Gas S/O Valve 1/25/2023 SGSOV Approved RYAN SALAZAR
Smoke Detectors 1/25/2023 Approved RYAN SALAZAR