5170 N GARDEN GROVE AVE 91356

Certificate Information: 5170 N GARDEN GROVE AVE 91356

Application / Permit
21014-20000-06344
Plan Check / Job No.
B21VN17686
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (177.5 SQ-FT ) TO & REMODEL SFD
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
CofO Issued on 10/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2021 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 MOHAMMAD ESMAILI
Corrections Issued 1/29/2022 MOHAMMAD ESMAILI
Quality Review Completed 2/9/2022 OMID HEDAYAT
Building Plans Picked Up 2/15/2022 APPLICANT
Plan Check Approved 4/28/2022 MOHAMMAD ESMAILI
Issued 4/28/2022 APPLICANT
CofO in Progress 10/6/2023 SEAN HAUPT
CofO Issued 10/20/2023 JOHN JANSON
Permit Finaled 10/20/2023 JOHN JANSON

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 3/3/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 3/3/2022 CARLOS AGUILERA
Sewer availability Cleared 3/3/2022 CARLOS AGUILERA
Grading Pre-Inspection Cleared 4/28/2022 MOHAMMAD ESMAILI

Contact Information

Contractor Owner-Builder       ,
Engineer Helou,, Dawn Renee; Lic. No.: C52361 22701 ERWIN ST      WOODLAND HILLS, CA 91367

Inspector Information

JOHN KIDWELL, (818) 774-4314 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/15/2022 Partial Approval DAVID SANDOVAL
Sewer 8/15/2022 Not Ready for Inspection DAVID SANDOVAL
Footing/Foundation/Slab 8/26/2022 Approved DAVID SANDOVAL
Deputy Reinf. Concrete 8/29/2022 Conditional Approval DAVID SANDOVAL
Wood Frame 10/3/2022 Corrections Issued JEFFREY BULL
Deputy Wood Construction 10/5/2022 Conditional Approval KRISTEN CAUSEY
BUILDING-Rough-Frame 12/15/2022 Approved DAVID SANDOVAL
ELECTRICAL-Rough 12/15/2022 Approved DAVID SANDOVAL
Green Building Rough 12/15/2022 Not Ready for Inspection DAVID SANDOVAL
HVAC-Rough 12/15/2022 Approved DAVID SANDOVAL
PLUMBING-Rough 12/15/2022 Approved DAVID SANDOVAL
Insulation 12/22/2022 Approved DAVID SANDOVAL
Interior/Exterior Lathing 12/22/2022 Partial Approval DAVID SANDOVAL
Shower Pan 12/22/2022 Corrections Issued DAVID SANDOVAL
Drywall Nailing 12/28/2022 Approved JESUS PINEDA
Shower Pan 12/28/2022 Approved JESUS PINEDA
Interior/Exterior Lathing 1/3/2023 Approved DAVID SANDOVAL
ELECTRICAL-Final 9/8/2023 Approved SEAN HAUPT
Gas Test 9/8/2023 Approved SEAN HAUPT
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Approved SEAN HAUPT
Service/Power Release 9/8/2023 Approved SEAN HAUPT
Smoke Detectors 9/8/2023 Approved SEAN HAUPT
BUILDING-Rough-Frame 9/22/2023 Approved JOHN KIDWELL
Final 9/22/2023 Not Ready for Inspection JOHN KIDWELL
Green Building Final 9/22/2023 Approved JOHN KIDWELL
Green Building Rough 9/22/2023 Approved JOHN KIDWELL
Final 10/5/2023 OK to Issue CofO SEAN HAUPT
PLUMBING-Final 10/5/2023 Approved SEAN HAUPT