2334 W LOY LANE 90041
Certificate Information: 2334 W LOY LANE 90041
- Application / Permit
- 21014-20000-06343
- Plan Check / Job No.
- B21VN17681
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 23'-10" X 12'-5", 293 SQ. FT. ADDITION OF A STUDY AND BATHROOM TO THE (E) 1-STORY SINGLE FAMILY DWELLING. ALL WORK PER ENGINEERING. SEE COMMENT [3]
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Current Status
- CofO Issued on 11/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2021 | COLIN LOREDO |
| Corrections Issued | 12/25/2021 | COLIN LOREDO |
| Building Plans Picked Up | 12/29/2021 | APPLICANT |
| Applicant returned to address corrections | 4/5/2022 | COLIN LOREDO |
| Plan Check Approved | 4/5/2022 | COLIN LOREDO |
| Issued | 4/29/2022 | APPLICANT |
| CofO in Progress | 10/30/2023 | SCOTT FINNILA |
| Permit Finaled | 11/2/2023 | DEROLD HAUFF |
| CofO Issued | 11/2/2023 | DEROLD HAUFF |
| Permit Finaled | 11/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/25/2022 | JEANIE LAM |
| Sewer availability | Cleared | 1/25/2022 | JEANIE LAM |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | JEANIE LAM |
| Grading Pre-Inspection | Cleared | 1/27/2022 | MANUEL TEJADA |
| ZA Case | Cleared | 2/8/2022 | MIGUEL GAMBOA |
Contact Information
| Contractor | M F Construction & Design Inc; Lic. No.: 762001-B | 2413 S 3RD AVENUE ARCADIA, CA 91006 |
| Engineer | Melchor,, Oscar Elias; Lic. No.: C76828 | 21243 VENTURA BLVD SUITE 119 WOODLAND HILLS, CA 91364 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 6/28/2022 | Approved | CRAIG VAUGHAN |
| METHANE-Barrier | 6/28/2022 | Approved | CRAIG VAUGHAN |
| METHANE-Subgrade | 6/28/2022 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 8/12/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Green Building Rough | 8/12/2022 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| METHANE-Rough | 8/12/2022 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/12/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 8/22/2022 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 8/22/2022 | Not Ready for Inspection | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 9/19/2022 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Rough | 9/19/2022 | Approved | SCOTT FINNILA |
| PLUMBING-Rough | 9/19/2022 | Approved | SCOTT FINNILA |
| BUILDING-Rough-Frame | 9/30/2022 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 9/30/2022 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 10/14/2022 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 10/14/2022 | Approved | CRAIG VAUGHAN |
| Final | 4/12/2023 | No Access for Inspection | CRAIG VAUGHAN |
| Green Building Final | 4/12/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 4/12/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Smoke Detectors | 4/12/2023 | No Access for Inspection | CRAIG VAUGHAN |
| Final | 6/22/2023 | Corrections Issued | BRIAN SULLIVAN |
| Smoke Detectors | 6/22/2023 | Approved | BRIAN SULLIVAN |
| Final | 6/26/2023 | Corrections Issued | BRIAN SULLIVAN |
| Final | 10/30/2023 | OK to Issue CofO | SCOTT FINNILA |