20748 W BURBANK BLVD 91367
Certificate Information: 20748 W BURBANK BLVD 91367
- Application / Permit
- 21014-20000-06309
- Plan Check / Job No.
- B21VN17607
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 27'-6" X 32'-1" IRREGULAR SHAPED ADDITION AND 8'-6" X 27'-5" ADDITION AND MAJOR REMODEL TO THE (E) SFD. NFPA 13D FIRE SPRINKLERS THROUGHOUT. ALL WORK PER ENGINEERING.
- Permit Issued
- Issued on 6/17/2022
- Issuing Office
- Current Status
- CofO Issued on 4/22/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/19/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/31/2022 | RAPHAEL ROSAS |
| Corrections Issued | 2/1/2022 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/27/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 5/28/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 6/1/2022 | APPLICANT |
| Issued | 6/17/2022 | APPLICANT |
| CofO in Progress | 2/27/2025 | ALEXANDER HANDY |
| Permit Finaled | 4/22/2025 | JOHN JANSON |
| CofO Issued | 4/22/2025 | JOHN JANSON |
| Permit Finaled | 4/22/2025 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/7/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 2/7/2022 | JOSE DUARTE-DIAZ |
| GPI Written Notices | Cleared | 5/3/2022 | BRIAN MILLER |
| Grading Pre-Inspection | Cleared | 5/17/2022 | BRIAN MILLER |
| Low Impact Development | Cleared | 5/18/2022 | AMMAR ELTAWIL |
| Roof/Waste drainage to street | Cleared | 5/19/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Standley,, Craig Erick; Lic. No.: C87675 | 5330 ZELZAH AVE UNIT 7 ENCINO, CA 91316 |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Other (see comments) | 6/30/2022 | Conditional Approval | STEVEN BACK |
| Special/Order Compliance | 6/30/2022 | Corrections Issued | STEVEN BACK |
| Excavation/Setback/Form/Re-Bar | 7/7/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 7/7/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 7/7/2022 | Partial Approval | STEVEN BACK |
| Deputy Reinf. Concrete | 7/8/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 7/20/2022 | Approved | STEVEN BACK |
| Deputy Reinf. Concrete | 7/21/2022 | Conditional Approval | JOHN JANSON |
| Deputy Reinf. Concrete | 7/26/2022 | Conditional Approval | JESUS PINEDA |
| Deputy Wood Construction | 8/30/2022 | Conditional Approval | STEVEN BACK |
| ELECTRICAL-Rough | 9/12/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2022 | Approved | STEVEN BACK |
| Green Building Rough | 9/12/2022 | Not Ready for Inspection | STEVEN BACK |
| HVAC-Rough | 9/12/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 9/12/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 10/13/2022 | Approved | STEVEN BACK |
| Green Building Rough | 10/13/2022 | Approved | STEVEN BACK |
| Insulation | 10/13/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/13/2022 | Partial Approval | STEVEN BACK |
| Special/Order Compliance | 10/13/2022 | Corrections Issued | STEVEN BACK |
| Verify Sprinkler Sign Off | 10/13/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 10/24/2022 | Approved | JEFFREY BULL |
| Shower Pan | 10/24/2022 | Approved | JEFFREY BULL |
| Drywall Nailing | 10/31/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 10/31/2022 | Approved | STEVEN BACK |
| Final | 1/29/2025 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 1/29/2025 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 1/29/2025 | SGSOV Approved | ALEXANDER HANDY |
| Smoke Detectors | 1/29/2025 | Approved | ALEXANDER HANDY |
| ELECTRICAL-Final | 2/26/2025 | Approved | ALEXANDER HANDY |
| Final | 2/26/2025 | OK to Issue CofO | ALEXANDER HANDY |
| HVAC-Final | 2/26/2025 | Approved | ALEXANDER HANDY |
| PLUMBING-Final | 2/26/2025 | Approved | ALEXANDER HANDY |