4219 S MOORE ST 90066

Certificate Information: 4219 S MOORE ST 90066

Application / Permit
21014-20000-06307
Plan Check / Job No.
B21VN17603
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
9'-6" X 9'-9" ADDITION OF LAUNDRY ROOM AND KITCHEN REMODEL TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 2/7/2022
Issuing Office
Current Status
CofO Issued on 12/21/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2021 APPLICANT
Assigned to Plan Check Engineer 12/21/2021 LUISANGEL VALENZUELA
Corrections Issued 12/21/2021 LUISANGEL VALENZUELA
Plan Check Approved 1/18/2022 LUISANGEL VALENZUELA
Building Plans Picked Up 1/18/2022 APPLICANT
Issued 2/7/2022 APPLICANT
CofO in Progress 12/9/2022 JESUS RODRIGUEZ
Permit Finaled 12/21/2022 DANIEL ORRANTE
CofO Issued 12/21/2022 DANIEL ORRANTE
Permit Finaled 12/21/2022 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/2/2022 DENNIS BRAGIN
Eng Process Fee Ord 176,300 Cleared 1/3/2022 DENNIS BRAGIN

Contact Information

Contractor Owner-Builder       ,
Engineer Baich,, Brendon Chad; Lic. No.: C83347 PO BOX 8840      POMONA, CA 91701

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/7/2022 Approved PATRICK QUALEY
PLUMBING-Rough 5/6/2022 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 5/11/2022 Corrections Issued CLAYTON GRAHAM
Deputy Wood Construction 5/27/2022 No Access for Inspection PATRICK QUALEY
ELECTRICAL-Rough 5/27/2022 Corrections Issued PATRICK QUALEY
Floor/Roof Diaphrgm/Shear Wall 5/27/2022 Corrections Issued PATRICK QUALEY
PLUMBING-Rough 6/8/2022 Corrections Issued PATRICK QUALEY
ELECTRICAL-Rough 6/14/2022 Approved JESUS RODRIGUEZ
HVAC-Rough 6/14/2022 Approved JESUS RODRIGUEZ
Wood Frame 6/14/2022 Approved JESUS RODRIGUEZ
PLUMBING-Rough 6/21/2022 Approved JESUS RODRIGUEZ
Interior/Exterior Lathing 6/24/2022 Approved JESUS RODRIGUEZ
Insulation 6/29/2022 Approved PATRICK QUALEY
Shower Pan 6/29/2022 Approved PATRICK QUALEY
Drywall Nailing 7/6/2022 Approved PATRICK QUALEY
BUILDING-Rough-Frame 11/22/2022 Approved JESUS RODRIGUEZ
Final 11/22/2022 Corrections Issued JESUS RODRIGUEZ
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Approved JESUS RODRIGUEZ
Smoke Detectors 11/22/2022 Approved JESUS RODRIGUEZ
ELECTRICAL-Final 11/23/2022 Approved JESUS RODRIGUEZ
Final 12/9/2022 OK to Issue CofO JESUS RODRIGUEZ
HVAC-Final 12/9/2022 Approved JESUS RODRIGUEZ
PLUMBING-Final 12/9/2022 Approved JESUS RODRIGUEZ