13620 N BORDEN AVE 91342

Certificate Information: 13620 N BORDEN AVE 91342

Application / Permit
21014-20000-06299
Plan Check / Job No.
B21VN17594
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 24'9" X 20' ADDITION TO (E) SFD FOR NEW BEDROOM ,BATHROOM AND DEN, INTERIOR REMODEL TO (E) SFD TO ADD (1) BEDROOM , (1) BATHROOM , ALL WORK PER WFPP
Permit Issued
Issued on 2/14/2022
Issuing Office
Current Status
CofO Issued on 2/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/20/2021 APPLICANT
Assigned to Plan Check Engineer 1/3/2022 RARES BODEA
Corrections Issued 1/6/2022 RARES BODEA
Building Plans Picked Up 1/10/2022 APPLICANT
Applicant returned to address corrections 2/10/2022 RARES BODEA
Plan Check Approved 2/14/2022 RARES BODEA
Issued 2/14/2022 APPLICANT
CofO in Progress 2/3/2023 ARAM AVEDISIAN
Permit Finaled 2/3/2023 MICHAEL SMITH
CofO Issued 2/3/2023 MICHAEL SMITH
Permit Finaled 2/3/2023 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/12/2022 AMIR KASHFI
Eng Process Fee Ord 176,300 Cleared 1/26/2022 AMIR KASHFI
Sewer availability Cleared 1/26/2022 AMIR KASHFI

Contact Information

Contractor Owner-Builder       ,

Inspector Information

KEVIN BERBERYAN, (818) 374-9931 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/18/2022 Partial Approval JOHN HAYES
Sewer 5/18/2022 Approved JOHN HAYES
Deputy Drilled-In Anchors 6/2/2022 Conditional Approval DEANDRE HOFFMAN
Footing/Foundation/Slab 6/2/2022 Approved JOHN HAYES
ELECTRICAL-Rough 7/15/2022 Partial Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 7/15/2022 Approved ARAM AVEDISIAN
HVAC-Rough 7/15/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 7/15/2022 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 7/21/2022 Approved ARAM AVEDISIAN
ELECTRICAL-Rough 7/21/2022 Approved ARAM AVEDISIAN
HVAC-Rough 7/21/2022 Approved ARAM AVEDISIAN
PLUMBING-Rough 7/21/2022 Approved ARAM AVEDISIAN
Insulation 7/29/2022 Approved ARAM AVEDISIAN
Interior/Exterior Lathing 7/29/2022 Not Ready for Inspection ARAM AVEDISIAN
Drywall Nailing 8/3/2022 Not Ready for Inspection DEANDRE HOFFMAN
Green Building Rough 8/3/2022 Not Ready for Inspection DEANDRE HOFFMAN
Interior/Exterior Lathing 8/3/2022 Not Ready for Inspection DEANDRE HOFFMAN
Drywall Nailing 8/8/2022 Approved CALEB MEISTER
Green Building Rough 8/8/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 8/8/2022 Approved CALEB MEISTER
Interior/Exterior Lathing 8/17/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 10/13/2022 Not Ready for Inspection THOMAS FINNILA
Smoke Detectors 10/13/2022 Not Ready for Inspection THOMAS FINNILA
ELECTRICAL-Final 11/22/2022 Approved ARAM AVEDISIAN
Final 11/22/2022 Corrections Issued ARAM AVEDISIAN
Green Building Final 11/22/2022 Approved ARAM AVEDISIAN
HVAC-Final 11/22/2022 Partial Approval ARAM AVEDISIAN
PLUMBING-Final 11/22/2022 Approved ARAM AVEDISIAN
SGSOV-Seismic Gas S/O Valve 11/22/2022 SGSOV Approved ARAM AVEDISIAN
Smoke Detectors 11/22/2022 Approved ARAM AVEDISIAN
Final 2/3/2023 OK to Issue CofO ARAM AVEDISIAN