13620 N BORDEN AVE 91342
Certificate Information: 13620 N BORDEN AVE 91342
- Application / Permit
- 21014-20000-06299
- Plan Check / Job No.
- B21VN17594
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 24'9" X 20' ADDITION TO (E) SFD FOR NEW BEDROOM ,BATHROOM AND DEN, INTERIOR REMODEL TO (E) SFD TO ADD (1) BEDROOM , (1) BATHROOM , ALL WORK PER WFPP
- Permit Issued
- Issued on 2/14/2022
- Issuing Office
- Current Status
- CofO Issued on 2/3/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/3/2022 | RARES BODEA |
| Corrections Issued | 1/6/2022 | RARES BODEA |
| Building Plans Picked Up | 1/10/2022 | APPLICANT |
| Applicant returned to address corrections | 2/10/2022 | RARES BODEA |
| Plan Check Approved | 2/14/2022 | RARES BODEA |
| Issued | 2/14/2022 | APPLICANT |
| CofO in Progress | 2/3/2023 | ARAM AVEDISIAN |
| Permit Finaled | 2/3/2023 | MICHAEL SMITH |
| CofO Issued | 2/3/2023 | MICHAEL SMITH |
| Permit Finaled | 2/3/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/12/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 1/26/2022 | AMIR KASHFI |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| KEVIN BERBERYAN, (818) 374-9931 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/18/2022 | Partial Approval | JOHN HAYES |
| Sewer | 5/18/2022 | Approved | JOHN HAYES |
| Deputy Drilled-In Anchors | 6/2/2022 | Conditional Approval | DEANDRE HOFFMAN |
| Footing/Foundation/Slab | 6/2/2022 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 7/15/2022 | Partial Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 7/15/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/15/2022 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 7/21/2022 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Rough | 7/21/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 7/21/2022 | Approved | ARAM AVEDISIAN |
| PLUMBING-Rough | 7/21/2022 | Approved | ARAM AVEDISIAN |
| Insulation | 7/29/2022 | Approved | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 7/29/2022 | Not Ready for Inspection | ARAM AVEDISIAN |
| Drywall Nailing | 8/3/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Green Building Rough | 8/3/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Interior/Exterior Lathing | 8/3/2022 | Not Ready for Inspection | DEANDRE HOFFMAN |
| Drywall Nailing | 8/8/2022 | Approved | CALEB MEISTER |
| Green Building Rough | 8/8/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 8/8/2022 | Approved | CALEB MEISTER |
| Interior/Exterior Lathing | 8/17/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Final | 10/13/2022 | Not Ready for Inspection | THOMAS FINNILA |
| Smoke Detectors | 10/13/2022 | Not Ready for Inspection | THOMAS FINNILA |
| ELECTRICAL-Final | 11/22/2022 | Approved | ARAM AVEDISIAN |
| Final | 11/22/2022 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 11/22/2022 | Approved | ARAM AVEDISIAN |
| HVAC-Final | 11/22/2022 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Final | 11/22/2022 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 11/22/2022 | Approved | ARAM AVEDISIAN |
| Final | 2/3/2023 | OK to Issue CofO | ARAM AVEDISIAN |