6953 N ZELZAH AVE 91335

Certificate Information: 6953 N ZELZAH AVE 91335

Application / Permit
21014-20000-06295
Plan Check / Job No.
B21VN17577
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) 18' X 20' DETACHED GARAGE AND ADD 10'-6" X 14' INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 5/4/2022
Issuing Office
Valley
Current Status
CofO Issued on 4/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/17/2021 APPLICANT
Assigned to Plan Check Engineer 12/23/2021 RAPHAEL ROSAS
Corrections Issued 12/24/2021 RAPHAEL ROSAS
Plan Check Approved 3/29/2022 RAPHAEL ROSAS
Building Plans Picked Up 3/30/2022 APPLICANT
Issued 5/4/2022 APPLICANT
CofO in Progress 4/19/2023 JEFFREY BULL
Permit Finaled 4/20/2023 JOHN JANSON
CofO Issued 4/20/2023 JOHN JANSON
Permit Finaled 4/20/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/27/2021 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 12/27/2021 CARLOS AGUILERA
Construction near power lines Cleared 3/12/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 3/16/2022 CARLOS AGUILERA
Sewer availability Cleared 3/16/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Christiansen,, Scott; Lic. No.: C37989 1003 WILSHIRE BLVD 202      SANTA MONICA, CA 90401

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/1/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 6/1/2022 Approved VINCENT HANLEY
PLUMBING-Rough 6/1/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 8/3/2022 Approved JEFFREY BULL
ELECTRICAL-Rough 8/16/2022 Approved JEFFREY BULL
HVAC-Rough 8/16/2022 Corrections Issued JEFFREY BULL
PLUMBING-Rough 8/16/2022 Approved JEFFREY BULL
HVAC-Rough 8/22/2022 Not Ready for Inspection DAVID SCANTLIN
Insulation 8/22/2022 Not Ready for Inspection DAVID SCANTLIN
Interior/Exterior Lathing 8/22/2022 Partial Approval DAVID SCANTLIN
Shower Pan 8/22/2022 Not Ready for Inspection DAVID SCANTLIN
Wood Frame 8/22/2022 Not Ready for Inspection DAVID SCANTLIN
Drywall Nailing 9/8/2022 Approved MORRIS JACKSON
Shower Pan 9/8/2022 Approved MORRIS JACKSON
Drywall Nailing 9/27/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 9/27/2022 Approved JEFFREY BULL
BUILDING-Rough-Frame 3/31/2023 Approved JEFFREY BULL
Final 3/31/2023 OK to Issue CofO JEFFREY BULL
Green Building Final 3/31/2023 Approved JEFFREY BULL
Green Building Rough 3/31/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 3/31/2023 SGSOV Approved JEFFREY BULL
Smoke Detectors 3/31/2023 Approved JEFFREY BULL