6031-6033 N FALLBROOK AVE 91367
Certificate Information: 6031-6033 N FALLBROOK AVE 91367
- Application / Permit
- 21014-20000-06290
- Plan Check / Job No.
- B21VN17559
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ePlan: CONVERT (E) GARAGE IN (E) SINGLE FAMILY DWELLING TO JUNIOR ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A) and 65852.22
- Permit Issued
- Issued on 2/8/2022
- Issuing Office
- Current Status
- CofO Issued on 6/24/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/17/2021 | DANIEL YIP |
| Corrections Issued | 12/21/2021 | DANIEL YIP |
| Applicant returned to address corrections | 1/19/2022 | DANIEL YIP |
| Applicant returned to address corrections | 1/28/2022 | DANIEL YIP |
| Plan Check Approved | 2/2/2022 | DANIEL YIP |
| Issued | 2/8/2022 | APPLICANT |
| CofO in Progress | 6/15/2022 | TROY SANDERS |
| Permit Finaled | 6/24/2022 | JOHN JANSON |
| CofO Issued | 6/24/2022 | JOHN JANSON |
| Permit Finaled | 6/24/2022 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 12/22/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/22/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | JOSE DUARTE-DIAZ |
| Grading Pre-Inspection | Cleared | 12/29/2021 | SERGIO VALENZUELA |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kazemi,, Milad; Lic. No.: C92143 | 21126 MERRIDY STREET CHATSWORTH, CA 91311 |
Inspector Information
| GEVORK IPCHYAN, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
| TROY SANDERS, (818) 774-4308 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 2/18/2022 | Approved | TROY SANDERS |
| Footing/Foundation/Slab | 2/28/2022 | Approved | TROY SANDERS |
| ELECTRICAL-Rough | 3/14/2022 | Approved | TROY SANDERS |
| Insulation | 3/14/2022 | Partial Approval | TROY SANDERS |
| Interior/Exterior Lathing | 3/14/2022 | Partial Approval | TROY SANDERS |
| PLUMBING-Rough | 3/14/2022 | Approved | TROY SANDERS |
| BUILDING-Rough-Frame | 3/23/2022 | Approved | TROY SANDERS |
| Green Building Rough | 3/23/2022 | Approved | TROY SANDERS |
| Insulation | 3/23/2022 | Approved | TROY SANDERS |
| Drywall Nailing | 4/6/2022 | Approved | JESUS PINEDA |
| ELECTRICAL-Final | 4/27/2022 | Approved | TROY SANDERS |
| PLUMBING-Final | 4/27/2022 | Not Ready for Inspection | TROY SANDERS |
| Smoke Detectors | 4/27/2022 | Approved | TROY SANDERS |
| Final | 5/24/2022 | Corrections Issued | TROY SANDERS |
| Green Building Final | 5/24/2022 | Approved | TROY SANDERS |
| HVAC-Final | 5/24/2022 | Approved | TROY SANDERS |
| PLUMBING-Final | 5/24/2022 | Approved | TROY SANDERS |
| Final | 6/14/2022 | OK to Issue CofO | TROY SANDERS |
| SGSOV-Seismic Gas S/O Valve | 6/14/2022 | SGSOV Approved | TROY SANDERS |
| Special/Order Compliance | 6/17/2022 | Corrections Issued | TROY SANDERS |