9911 W COVELLO ST 91504

Certificate Information: 9911 W COVELLO ST 91504

Application / Permit
21014-20000-06289
Plan Check / Job No.
B21VN17557
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED ADU WITH PATIO COVER PER DETACHED ADU ORDINANCE
Permit Issued
Issued on 7/26/2022
Issuing Office
Current Status
CofO Issued on 11/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/16/2021 APPLICANT
Assigned to Plan Check Engineer 12/17/2021 JOE VO
Corrections Issued 12/17/2021 CARLOS MONTES
Applicant returned to address corrections 6/27/2022 CARLOS MONTES
Applicant returned to address corrections 7/8/2022 JOE VO
Plan Check Approved 7/26/2022 JOE VO
Issued 7/26/2022 APPLICANT
CofO in Progress 10/6/2023 DAVID ANDERSON
Permit Finaled 11/25/2023 RUBEN SALAS
CofO Issued 11/25/2023 RUBEN SALAS
Permit Finaled 11/25/2023 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 2/22/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 2/23/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 2/23/2022 JOSE DUARTE-DIAZ
Construction near power lines Cleared 4/8/2022 RIDWAN HARDY
Low Impact Development Cleared 6/22/2022 TA ANH
Roof/Waste drainage to street Cleared 6/24/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

MATTHEW NELSON, (818) 374-1168 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/1/2022 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 9/8/2022 Partial Approval DAVID ANDERSON
Footing/Foundation/Slab 9/16/2022 Approved DAVID ANDERSON
BUILDING-Rough-Frame 10/12/2022 Not Ready for Inspection DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 10/12/2022 Approved DAVID ANDERSON
Green Building Rough 10/12/2022 Not Ready for Inspection DAVID ANDERSON
MERV13>=Rough 10/12/2022 Not Ready for Inspection DAVID ANDERSON
BUILDING-Rough-Frame 11/18/2022 Not Ready for Inspection DAVID ANDERSON
Green Building Rough 11/18/2022 Approved DAVID ANDERSON
MERV13>=Rough 11/18/2022 Approved DAVID ANDERSON
Verify Sprinkler Sign Off 11/18/2022 Approved DAVID ANDERSON
ELECTRICAL-Rough 11/21/2022 Corrections Issued DAVID ANDERSON
Floor/Roof Diaphrgm/Shear Wall 11/21/2022 Approved DAVID ANDERSON
HVAC-Rough 11/21/2022 Corrections Issued DAVID ANDERSON
PLUMBING-Rough 11/21/2022 Approved DAVID ANDERSON
Interior/Exterior Lathing 12/5/2022 Approved DAVID ANDERSON
Insulation 12/19/2022 Approved DAVID ANDERSON
Drywall Nailing 1/3/2023 Approved DAVID ANDERSON
BUILDING-Rough-Frame 5/11/2023 Approved DAVID ANDERSON
ELECTRICAL-Rough 6/13/2023 Corrections Issued DAVID ANDERSON
Final 10/5/2023 OK to Issue CofO DAVID ANDERSON
Green Building Final 10/5/2023 Approved DAVID ANDERSON
MERV13>=Final 10/5/2023 Approved DAVID ANDERSON
SGSOV-Seismic Gas S/O Valve 10/5/2023 SGSOV Approved DAVID ANDERSON
Service/Power Release 10/5/2023 Approved DAVID ANDERSON
Smoke Detectors 10/5/2023 Approved DAVID ANDERSON