6320 N KRAFT AVE 91606
Certificate Information: 6320 N KRAFT AVE 91606
- Application / Permit
- 21014-20000-06285
- Plan Check / Job No.
- B21VN17544
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 48 SQ. FT. ADDITION AND INTERIOR REMODEL TO THE (E) SFD PER ENGINEERING.
- Permit Issued
- Issued on 4/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 10/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/10/2022 | COLIN LOREDO |
| Corrections Issued | 1/11/2022 | COLIN LOREDO |
| Applicant returned to address corrections | 2/2/2022 | COLIN LOREDO |
| Plan Check Approved | 2/24/2022 | COLIN LOREDO |
| Building Plans Picked Up | 2/25/2022 | APPLICANT |
| Issued | 4/14/2022 | APPLICANT |
| CofO in Progress | 10/2/2023 | ROBERT GOLD |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
| CofO Issued | 10/13/2023 | RUBEN SALAS |
| Permit Finaled | 10/13/2023 | RUBEN SALAS |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/13/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/19/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Design Wall Systems Incorporated; Lic. No.: 810493-B | 543 PASEO GRANDE THOUSAND OAKS, CA 91320 |
| Engineer | Roberts,, Jeffrey Allan; Lic. No.: C56881 | 8325 FOOTHILL BLVD. STE A SUNLAND, CA 91040 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 10/4/2022 | Approved | JOHN HAYES |
| Green Building Rough | 10/4/2022 | Approved | JOHN HAYES |
| Rough-Elec/Plmb/HVAC | 10/4/2022 | Approved | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 1/19/2023 | Corrections Issued | JOHN HAYES |
| Excavation/Setback/Form/Re-Bar | 2/3/2023 | Approved | JOHN HAYES |
| ELECTRICAL-Rough | 3/24/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Floor/Roof Diaphrgm/Shear Wall | 3/24/2023 | Partial Approval | JENNIFER RABUCHIN |
| PLUMBING-Rough | 3/24/2023 | Corrections Issued | JENNIFER RABUCHIN |
| Wood Frame | 3/24/2023 | Corrections Issued | JENNIFER RABUCHIN |
| ELECTRICAL-Rough | 3/31/2023 | Approved | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 3/31/2023 | Partial Approval | ROBERT GOLD |
| HVAC-Rough | 3/31/2023 | Corrections Issued | ROBERT GOLD |
| PLUMBING-Rough | 3/31/2023 | Approved | ROBERT GOLD |
| Wood Frame | 3/31/2023 | Corrections Issued | ROBERT GOLD |
| BUILDING-Rough-Frame | 4/18/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 4/18/2023 | Partial Approval | CHRISTOPHER DELLEFIELD |
| HVAC-Rough | 4/18/2023 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 4/20/2023 | Partial Approval | JOHN COLEMAN |
| Insulation | 4/26/2023 | Not Ready for Inspection | JOHN HAYES |
| Interior/Exterior Lathing | 4/26/2023 | Not Ready for Inspection | JOHN HAYES |
| Shower Pan | 4/26/2023 | Not Ready for Inspection | JOHN HAYES |
| Special/Order Compliance | 4/26/2023 | Corrections Issued | JOHN HAYES |
| BUILDING-Rough-Frame | 5/1/2023 | Approved | ROBERT GOLD |
| Floor/Roof Diaphrgm/Shear Wall | 5/1/2023 | Approved | ROBERT GOLD |
| Insulation | 5/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| Interior/Exterior Lathing | 5/1/2023 | Not Ready for Inspection | ROBERT GOLD |
| Shower Pan | 5/1/2023 | Approved | ROBERT GOLD |
| Insulation | 5/5/2023 | Approved | JOHN HAYES |
| Interior/Exterior Lathing | 5/5/2023 | Partial Approval | JOHN HAYES |
| Drywall Nailing | 5/17/2023 | Approved | ROBERT GOLD |
| Interior/Exterior Lathing | 5/17/2023 | Approved | ROBERT GOLD |
| Excavation/Setback/Form/Re-Bar | 8/15/2023 | Partial Approval | DAVID MATSON |
| ELECTRICAL-Final | 9/20/2023 | Not Ready for Inspection | ROBERT GOLD |
| Final | 9/20/2023 | Corrections Issued | ROBERT GOLD |
| Footing/Foundation/Slab | 9/20/2023 | Approved | ROBERT GOLD |
| Green Building Final | 9/20/2023 | Approved | ROBERT GOLD |
| HVAC-Final | 9/20/2023 | Approved | ROBERT GOLD |
| PLUMBING-Final | 9/20/2023 | Not Ready for Inspection | ROBERT GOLD |
| SGSOV-Seismic Gas S/O Valve | 9/20/2023 | SGSOV Approved | ROBERT GOLD |
| Smoke Detectors | 9/20/2023 | Approved | ROBERT GOLD |
| ELECTRICAL-Final | 9/22/2023 | Not Ready for Inspection | ROBERT GOLD |
| HVAC-Final | 9/22/2023 | Approved | ROBERT GOLD |
| PLUMBING-Final | 9/22/2023 | Not Ready for Inspection | ROBERT GOLD |
| Final | 10/2/2023 | OK to Issue CofO | ROBERT GOLD |