6320 N KRAFT AVE 91606

Certificate Information: 6320 N KRAFT AVE 91606

Application / Permit
21014-20000-06285
Plan Check / Job No.
B21VN17544
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
48 SQ. FT. ADDITION AND INTERIOR REMODEL TO THE (E) SFD PER ENGINEERING.
Permit Issued
Issued on 4/14/2022
Issuing Office
Valley
Current Status
CofO Issued on 10/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/28/2021 APPLICANT
Assigned to Plan Check Engineer 1/10/2022 COLIN LOREDO
Corrections Issued 1/11/2022 COLIN LOREDO
Applicant returned to address corrections 2/2/2022 COLIN LOREDO
Plan Check Approved 2/24/2022 COLIN LOREDO
Building Plans Picked Up 2/25/2022 APPLICANT
Issued 4/14/2022 APPLICANT
CofO in Progress 10/2/2023 ROBERT GOLD
Permit Finaled 10/13/2023 RUBEN SALAS
CofO Issued 10/13/2023 RUBEN SALAS
Permit Finaled 10/13/2023 RUBEN SALAS

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/13/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 1/19/2022 CARLOS AGUILERA

Contact Information

Contractor Design Wall Systems Incorporated; Lic. No.: 810493-B 543 PASEO GRANDE      THOUSAND OAKS, CA 91320
Engineer Roberts,, Jeffrey Allan; Lic. No.: C56881 8325 FOOTHILL BLVD. STE A      SUNLAND, CA 91040

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

BUILDING-Rough-Frame 10/4/2022 Approved JOHN HAYES
Green Building Rough 10/4/2022 Approved JOHN HAYES
Rough-Elec/Plmb/HVAC 10/4/2022 Approved JOHN HAYES
Excavation/Setback/Form/Re-Bar 1/19/2023 Corrections Issued JOHN HAYES
Excavation/Setback/Form/Re-Bar 2/3/2023 Approved JOHN HAYES
ELECTRICAL-Rough 3/24/2023 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/24/2023 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 3/24/2023 Corrections Issued JENNIFER RABUCHIN
Wood Frame 3/24/2023 Corrections Issued JENNIFER RABUCHIN
ELECTRICAL-Rough 3/31/2023 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 3/31/2023 Partial Approval ROBERT GOLD
HVAC-Rough 3/31/2023 Corrections Issued ROBERT GOLD
PLUMBING-Rough 3/31/2023 Approved ROBERT GOLD
Wood Frame 3/31/2023 Corrections Issued ROBERT GOLD
BUILDING-Rough-Frame 4/18/2023 Partial Approval CHRISTOPHER DELLEFIELD
Footing/Foundation/Slab 4/18/2023 Partial Approval CHRISTOPHER DELLEFIELD
HVAC-Rough 4/18/2023 Approved CHRISTOPHER DELLEFIELD
Floor/Roof Diaphrgm/Shear Wall 4/20/2023 Partial Approval JOHN COLEMAN
Insulation 4/26/2023 Not Ready for Inspection JOHN HAYES
Interior/Exterior Lathing 4/26/2023 Not Ready for Inspection JOHN HAYES
Shower Pan 4/26/2023 Not Ready for Inspection JOHN HAYES
Special/Order Compliance 4/26/2023 Corrections Issued JOHN HAYES
BUILDING-Rough-Frame 5/1/2023 Approved ROBERT GOLD
Floor/Roof Diaphrgm/Shear Wall 5/1/2023 Approved ROBERT GOLD
Insulation 5/1/2023 Not Ready for Inspection ROBERT GOLD
Interior/Exterior Lathing 5/1/2023 Not Ready for Inspection ROBERT GOLD
Shower Pan 5/1/2023 Approved ROBERT GOLD
Insulation 5/5/2023 Approved JOHN HAYES
Interior/Exterior Lathing 5/5/2023 Partial Approval JOHN HAYES
Drywall Nailing 5/17/2023 Approved ROBERT GOLD
Interior/Exterior Lathing 5/17/2023 Approved ROBERT GOLD
Excavation/Setback/Form/Re-Bar 8/15/2023 Partial Approval DAVID MATSON
ELECTRICAL-Final 9/20/2023 Not Ready for Inspection ROBERT GOLD
Final 9/20/2023 Corrections Issued ROBERT GOLD
Footing/Foundation/Slab 9/20/2023 Approved ROBERT GOLD
Green Building Final 9/20/2023 Approved ROBERT GOLD
HVAC-Final 9/20/2023 Approved ROBERT GOLD
PLUMBING-Final 9/20/2023 Not Ready for Inspection ROBERT GOLD
SGSOV-Seismic Gas S/O Valve 9/20/2023 SGSOV Approved ROBERT GOLD
Smoke Detectors 9/20/2023 Approved ROBERT GOLD
ELECTRICAL-Final 9/22/2023 Not Ready for Inspection ROBERT GOLD
HVAC-Final 9/22/2023 Approved ROBERT GOLD
PLUMBING-Final 9/22/2023 Not Ready for Inspection ROBERT GOLD
Final 10/2/2023 OK to Issue CofO ROBERT GOLD