12654 W WELBY WAY 91606
Certificate Information: 12654 W WELBY WAY 91606
- Application / Permit
- 21014-20000-06273
- Plan Check / Job No.
- B21VN17524
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePlan: ADDITION TO (E) GARAGE AND CONVERT TO ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 6/30/2023
- Issuing Office
- Current Status
- CofO Issued on 4/10/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/18/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/20/2022 | DANIEL YIP |
| Corrections Issued | 1/24/2022 | DANIEL YIP |
| Quality Review Completed | 1/24/2022 | LIPING TENG |
| Plan Check Approved | 8/16/2022 | DANIEL YIP |
| Issued | 6/30/2023 | APPLICANT |
| CofO in Progress | 3/27/2025 | GAREN HAYRAPETYAN |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
| CofO Issued | 4/10/2025 | RUBEN SALAS |
| Permit Finaled | 4/10/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Construction near power lines | Cleared | 7/12/2022 | WALTER RAMIREZ |
| Address approval | Cleared | 7/14/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 7/18/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 7/21/2022 | ROGELIO CORTES |
| Sewer availability | Cleared | 7/21/2022 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 7/22/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | A N S Construction Company; Lic. No.: 980506-B | , |
Inspector Information
| WAYNE REGESTER, (818) 374-1164 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 1/16/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 2/6/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Deputy Drilled-In Anchors | 2/12/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 2/13/2024 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 2/16/2024 | Partial Approval | JOSE AVILA |
| Underground Mechanical | 3/6/2024 | Partial Inspection | MISAEL ESPARZA |
| PLUMBING-Rough | 3/11/2024 | Corrections Issued | JOSE AVILA |
| PLUMBING-Rough | 3/15/2024 | Partial Approval | JOSE AVILA |
| Deputy Drilled-In Anchors | 5/13/2024 | Conditional Approval | JUAN VALENZUELA |
| Footing/Foundation/Slab | 5/17/2024 | Corrections Issued | JOHN COLEMAN |
| Underground Mechanical | 5/17/2024 | Approved | JOHN COLEMAN |
| Deputy Drilled-In Anchors | 5/24/2024 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 5/29/2024 | Approved | OGANES TARAKHCHYAN |
| Wood Frame | 6/21/2024 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Rough | 7/9/2024 | Approved | OGANES TARAKHCHYAN |
| HVAC-Rough | 7/9/2024 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Rough | 7/9/2024 | Corrections Issued | OGANES TARAKHCHYAN |
| Deputy Wood Construction | 7/10/2024 | Conditional Approval | JUAN VALENZUELA |
| BUILDING-Rough-Frame | 7/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| Green Building Rough | 7/19/2024 | Not Ready for Inspection | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 7/19/2024 | Corrections Issued | ROBERTO PALACIOS-LOPEZ |
| PLUMBING-Rough | 7/19/2024 | Approved | ROBERTO PALACIOS-LOPEZ |
| Interior/Exterior Lathing | 7/23/2024 | Corrections Issued | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 7/25/2024 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 7/25/2024 | Approved | OGANES TARAKHCHYAN |
| Interior/Exterior Lathing | 7/25/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Insulation | 8/6/2024 | Approved | CHRISTOPHE COCHRAN |
| Shower Pan | 8/6/2024 | Approved | CHRISTOPHE COCHRAN |
| Drywall Nailing | 8/16/2024 | Approved | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 8/16/2024 | Approved | SALVADOR MARTINEZ |
| Special/Order Compliance | 9/9/2024 | Partial Approval | OGANES TARAKHCHYAN |
| Service/Power Release | 12/2/2024 | Not Ready for Inspection | OGANES TARAKHCHYAN |
| Service/Power Release | 12/6/2024 | Not Ready for Inspection | GAREN HAYRAPETYAN |
| Final | 3/27/2025 | OK to Issue CofO | GAREN HAYRAPETYAN |
| Green Building Final | 3/27/2025 | Approved | GAREN HAYRAPETYAN |
| SGSOV-Seismic Gas S/O Valve | 3/27/2025 | SGSOV Approved | GAREN HAYRAPETYAN |
| Service/Power Release | 3/27/2025 | Approved | GAREN HAYRAPETYAN |
| Smoke Detectors | 3/27/2025 | Approved | GAREN HAYRAPETYAN |