925 E 91ST ST 90002

Certificate Information: 925 E 91ST ST 90002

Application / Permit
21014-20000-06237
Plan Check / Job No.
B21VN17454
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
*EPLAN* ADD 26'-8" X 25'-5" TO AND CONVERT EXISTING DETACHED GARAGE TO NEW ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d)
Permit Issued
Issued on 9/28/2023
Issuing Office
Current Status
CofO Issued on 11/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2022 APPLICANT
Assigned to Plan Check Engineer 1/11/2022 SELLA BENYAMIN
Corrections Issued 1/12/2022 SELLA BENYAMIN
Applicant returned to address corrections 11/17/2022 SELLA BENYAMIN
Plan Check Approved 12/1/2022 SELLA BENYAMIN
Issued 9/28/2023 APPLICANT
CofO in Progress 10/29/2025 JOHN QUINTANILLA
No Progress 10/29/2025 MICHAEL LEWIS
CofO in Progress 10/29/2025 MICHAEL LEWIS
Permit Finaled 11/9/2025 DEROLD HAUFF
CofO Issued 11/9/2025 DEROLD HAUFF
Permit Finaled 11/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/20/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 5/3/2022 AMY SHUM
Sewer availability Cleared 10/22/2022 JEANETTE VONG
Low Impact Development Cleared 11/17/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 12/1/2022 THAN WIN

Contact Information

Contractor Owner-Builder       ,
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 4/15/2024 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 5/2/2024 Not Ready for Inspection MICHAEL LEWIS
Underground Mechanical 5/2/2024 Approved MICHAEL LEWIS
Excavation/Setback/Form/Re-Bar 5/9/2024 Corrections Issued MICHAEL LEWIS
Footing/Foundation/Slab 5/21/2024 Approved MICHAEL LEWIS
BUILDING-Rough-Frame 5/28/2024 Not Ready for Inspection CRAIG DAVIS
Floor/Roof Diaphrgm/Shear Wall 5/28/2024 Partial Approval CRAIG DAVIS
Green Building Rough 5/28/2024 Not Ready for Inspection CRAIG DAVIS
Wood Frame 5/28/2024 Not Ready for Inspection CRAIG DAVIS
BUILDING-Rough-Frame 6/11/2024 Not Ready for Inspection JOSEPH MCGARRY
ELECTRICAL-Rough 6/11/2024 Corrections Issued JOSEPH MCGARRY
Green Building Rough 6/11/2024 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 6/11/2024 Approved JOSEPH MCGARRY
BUILDING-Rough-Frame 6/17/2024 Corrections Issued MICHAEL LEWIS
ELECTRICAL-Rough 6/17/2024 Approved MICHAEL LEWIS
Green Building Rough 6/17/2024 Corrections Issued MICHAEL LEWIS
HVAC-Rough 6/17/2024 Corrections Issued MICHAEL LEWIS
BUILDING-Rough-Frame 6/21/2024 Approved MICHAEL LEWIS
Green Building Rough 6/21/2024 Approved MICHAEL LEWIS
HVAC-Rough 6/21/2024 Approved MICHAEL LEWIS
Insulation 6/26/2024 Corrections Issued MICHAEL LEWIS
Insulation 7/3/2024 Approved MICHAEL LEWIS
Interior/Exterior Lathing 7/3/2024 Approved MICHAEL LEWIS
Drywall Nailing 7/10/2024 Approved MICHAEL LEWIS
Shower Pan 7/29/2024 Approved ALEX COLIN
Sewer 11/15/2024 Approved MICHAEL LEWIS
Underground Mechanical 11/15/2024 Approved MICHAEL LEWIS
Pre-Inspection 6/12/2025 Not Ready for Inspection JOHN QUINTANILLA
Final 10/14/2025 No Access for Inspection JOHN QUINTANILLA
Green Building Final 10/14/2025 No Access for Inspection JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 10/14/2025 SGSOV Not Ready JOHN QUINTANILLA
Smoke Detectors 10/14/2025 No Access for Inspection JOHN QUINTANILLA
Pre-Inspection 10/21/2025 Corrections Issued JOHN QUINTANILLA
Final 10/23/2025 OK to Issue CofO JOHN QUINTANILLA
Green Building Final 10/23/2025 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 10/23/2025 SGSOV Approved JOHN QUINTANILLA
Smoke Detectors 10/23/2025 Approved JOHN QUINTANILLA