6909-6911 N AMIGO AVE 91335

Certificate Information: 6909-6911 N AMIGO AVE 91335

Application / Permit
21014-20000-06235
Plan Check / Job No.
B21VN17432
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
CONVERT (E) ATTACHED GARAGE TO ACCESSORY DWELLING UNIT WITH 2ND STORY ADDITION PER LAMC 12.22A33(c)AND(d). ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/17/2022
Issuing Office
Current Status
CofO Issued on 10/11/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2021 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 COLIN LOREDO
Corrections Issued 2/3/2022 COLIN LOREDO
Quality Review Completed 2/7/2022 OMID HEDAYAT
Building Plans Picked Up 2/7/2022 APPLICANT
Plan Check Approved 2/28/2022 COLIN LOREDO
Issued 3/17/2022 APPLICANT
CofO in Progress 5/25/2023 JEFFREY BULL
Permit Finaled 10/11/2023 JOHN JANSON
CofO Issued 10/11/2023 JOHN JANSON
Permit Finaled 10/11/2023 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 2/16/2022 CARLOS AGUILERA
Roof/Waste drainage to street Cleared 2/16/2022 CARLOS AGUILERA
ZA Case Cleared 2/16/2022 MIGUEL GAMBOA
ZI Cleared 2/16/2022 MIGUEL GAMBOA
Eng Process Fee Ord 176,300 Cleared 3/1/2022 ROSE MARIE SMITH
Sewer availability Cleared 3/1/2022 ROSE MARIE SMITH

Contact Information

Contractor Owner-Builder       ,
Engineer Chatsky,, German; Lic. No.: C84153 6541 ODESSA AVE UNIT 11      LAKE BALBOA, CA 91406

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/22/2022 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 4/5/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/5/2022 Approved VINCENT HANLEY
Deputy Steel/Welding 4/7/2022 Approved VINCENT HANLEY
Reinforced Concrete Frame 4/8/2022 Approved VINCENT HANLEY
Structural Steel Frame 4/8/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 4/13/2022 Partial Approval VINCENT HANLEY
Wood Frame 4/18/2022 Not Ready for Inspection VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/22/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 4/27/2022 Corrections Issued VINCENT HANLEY
Wood Frame 4/27/2022 Corrections Issued VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/17/2022 Partial Approval VINCENT HANLEY
HVAC-Rough 5/17/2022 Not Ready for Inspection VINCENT HANLEY
PLUMBING-Rough 5/17/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 6/1/2022 Approved VINCENT HANLEY
HVAC-Rough 6/1/2022 Approved VINCENT HANLEY
PLUMBING-Rough 6/1/2022 Approved VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 6/6/2022 Approved VINCENT HANLEY
Wood Frame 6/6/2022 Approved VINCENT HANLEY
Deputy Wood Construction 6/14/2022 Partial Approval JEFFREY BULL
Deputy Steel/Welding 6/17/2022 Conditional Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 6/21/2022 Approved JEFFREY BULL
Shower Pan 6/21/2022 Approved JEFFREY BULL
Insulation 6/30/2022 Approved JEFFREY BULL
Interior/Exterior Lathing 6/30/2022 Approved JEFFREY BULL
Drywall Nailing 7/6/2022 Approved JEFFREY BULL
Green Building Rough 7/6/2022 Approved JEFFREY BULL
BUILDING-Rough-Frame 10/14/2022 Approved JEFFREY PARD
ELECTRICAL-Final 10/14/2022 Not Ready for Inspection JEFFREY PARD
Final 10/14/2022 Not Ready for Inspection JEFFREY PARD
Green Building Final 10/14/2022 Corrections Issued JEFFREY PARD
SGSOV-Seismic Gas S/O Valve 10/14/2022 SGSOV Not Ready JEFFREY PARD
Smoke Detectors 10/14/2022 Approved JEFFREY PARD
Final 10/31/2022 Corrections Issued JEFFREY BULL
Green Building Final 10/31/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Not Ready JEFFREY BULL
Final 4/20/2023 Corrections Issued JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 4/20/2023 SGSOV Approved JEFFREY BULL
Final 5/25/2023 OK to Issue CofO JEFFREY BULL