10625 W ARTRUDE ST 91040
Certificate Information: 10625 W ARTRUDE ST 91040
- Application / Permit
- 21014-20000-06225
- Plan Check / Job No.
- B21VN17374
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (7) Garage - Private
- Work Description
- CONVERT (E) STORAGE INTO RECREATION ROOM W/(94 SQFT) STORAGE ADDITION,W/ NEW 295 SQFT PATIO TO (E) DETACHED GARAGE AT REAR OF LOT PER ENGINEERING DESIGN
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- CofO Issued on 4/11/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2021 | PETER MOSESIAN |
| Corrections Issued | 12/16/2021 | PETER MOSESIAN |
| Building Plans Picked Up | 12/21/2021 | APPLICANT |
| Applicant returned to address corrections | 3/7/2022 | PETER MOSESIAN |
| Issued | 4/1/2022 | APPLICANT |
| CofO in Progress | 4/4/2023 | DAVID ANDERSON |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
| CofO Issued | 4/11/2023 | MICHAEL SMITH |
| Permit Finaled | 4/11/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/21/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/22/2021 | JOSE DUARTE-DIAZ |
| Construction near power lines | Cleared | 12/27/2021 | WALTER RAMIREZ |
| Grading Pre-Inspection | Cleared | 1/4/2022 | BRIAN MILLER |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Nazarians,, Harmick Edward; Lic. No.: C91232 | 9825 OSO AVE CHATSWORTH, CA 91311 |
Inspector Information
| MATTHEW NELSON, (818) 374-1168 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 4/26/2022 | Partial Approval | WILLIAM WREN |
| Deputy Drilled-In Anchors | 5/4/2022 | Conditional Approval | WILLIAM KUEHN |
| Excavation/Setback/Form/Re-Bar | 5/6/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 5/6/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 6/6/2022 | Partial Approval | MATTHEW NELSON |
| Green Building Rough | 6/6/2022 | Not Ready for Inspection | MATTHEW NELSON |
| Floor/Roof Diaphrgm/Shear Wall | 6/23/2022 | Approved | DAVID ANDERSON |
| Underground Mechanical | 6/30/2022 | Approved | DAVID ANDERSON |
| Interior/Exterior Lathing | 7/5/2022 | Off-Hour Fees Due | |
| Interior/Exterior Lathing | 7/7/2022 | Approved | DAVID ANDERSON |
| BUILDING-Rough-Frame | 7/20/2022 | Approved | DAVID ANDERSON |
| Green Building Rough | 7/20/2022 | Approved | DAVID ANDERSON |
| Rough-Elec/Plmb/HVAC | 7/20/2022 | Approved | DAVID ANDERSON |
| Drywall Nailing | 9/19/2022 | Approved | DAVID ANDERSON |
| Final | 4/3/2023 | OK to Issue CofO | DAVID ANDERSON |
| Green Building Final | 4/3/2023 | Approved | DAVID ANDERSON |
| SGSOV-Seismic Gas S/O Valve | 4/3/2023 | SGSOV Not Required | DAVID ANDERSON |
| Smoke Detectors | 4/3/2023 | Approved | DAVID ANDERSON |