4826 S VAN NESS AVE 90062
Certificate Information: 4826 S VAN NESS AVE 90062
- Application / Permit
- 21014-20000-06223
- Plan Check / Job No.
- B21VN17368
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT THE (E) DETACHED GARAGE TO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d) AND AN 11'3" x16' ADDITION, TOTALING 468 SF. DESIGN PER WFPP.
- Permit Issued
- Issued on 3/24/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 4/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 1/4/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 1/19/2022 | LUIS RINCON |
| Corrections Issued | 1/22/2022 | LUIS RINCON |
| Applicant returned to address corrections | 3/4/2022 | LUIS RINCON |
| Plan Check Approved | 3/24/2022 | LUIS RINCON |
| Issued | 3/24/2022 | APPLICANT |
| Building Plans Picked Up | 3/25/2022 | APPLICANT |
| CofO in Progress | 4/18/2024 | CRAIG DAVIS |
| Permit Finaled | 4/18/2024 | DEROLD HAUFF |
| CofO Issued | 4/18/2024 | DEROLD HAUFF |
| Permit Finaled | 4/18/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/31/2022 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 1/31/2022 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 1/31/2022 | CINDY QI |
| Sewer availability | Cleared | 1/31/2022 | CINDY QI |
Contact Information
| No Data Available. |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/7/2022 | Approved | HORACE FULTZ |
| PLUMBING-Rough | 7/7/2022 | Partial Approval | HORACE FULTZ |
| BUILDING-Rough-Frame | 8/5/2022 | No Access for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 8/5/2022 | No Access for Inspection | SABAS ALONSO |
| Green Building Rough | 8/5/2022 | No Access for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 8/5/2022 | No Access for Inspection | SABAS ALONSO |
| Underground Mechanical | 8/5/2022 | No Access for Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/10/2022 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 8/10/2022 | Approved | SABAS ALONSO |
| Green Building Rough | 8/10/2022 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 8/10/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 8/10/2022 | Partial Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/15/2022 | Not Ready for Inspection | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/15/2022 | Partial Approval | HORACE FULTZ |
| Green Building Rough | 8/15/2022 | Approved | HORACE FULTZ |
| Deputy Wood Construction | 8/24/2022 | Conditional Approval | SABAS ALONSO |
| BUILDING-Rough-Frame | 8/29/2022 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/29/2022 | Approved | SABAS ALONSO |
| HVAC-Rough | 8/29/2022 | Approved | SABAS ALONSO |
| Insulation | 9/2/2022 | Approved | ANDREW BEELI |
| Interior/Exterior Lathing | 9/2/2022 | Approved | ANDREW BEELI |
| Drywall Nailing | 9/9/2022 | Approved | HORACE FULTZ |
| Interior/Exterior Lathing | 9/28/2022 | Approved | ANTHONY EGSON |
| Gas Test | 11/2/2023 | Approved | CRAIG DAVIS |
| Final | 12/12/2023 | Not Ready for Inspection | CRAIG DAVIS |
| Green Building Final | 12/12/2023 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 12/12/2023 | SGSOV Not Ready | CRAIG DAVIS |
| Smoke Detectors | 12/12/2023 | Approved | CRAIG DAVIS |
| Final | 1/9/2024 | Corrections Issued | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/9/2024 | SGSOV Approved | ANTHONY EGSON |
| Final | 1/25/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 2/2/2024 | Corrections Issued | RONNIE MINDANAO |
| Final | 3/7/2024 | Not Ready for Inspection | JOSEPH MCGARRY |
| Final | 4/8/2024 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Final | 4/17/2024 | Approved | CRAIG DAVIS |
| Final | 4/17/2024 | OK to Issue CofO | CRAIG DAVIS |
| HVAC-Final | 4/17/2024 | Approved | CRAIG DAVIS |
| PLUMBING-Final | 4/17/2024 | Approved | CRAIG DAVIS |
| SGSOV-Seismic Gas S/O Valve | 4/17/2024 | SGSOV Approved | CRAIG DAVIS |
| Service/Power Release | 4/17/2024 | Approved | CRAIG DAVIS |