457 N JUNE ST 90004
Certificate Information: 457 N JUNE ST 90004
- Application / Permit
- 21014-20000-06221
- Plan Check / Job No.
- B21VN17366
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) DETACHED GARAGE WITH STORAGE TO ACCESSORY DWELLING UNIT WITH ADDITION PER STATE LAW
- Permit Issued
- Issued on 5/2/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | JEROME MAGAT PALMA |
| Corrections Issued | 12/25/2021 | JEROME MAGAT PALMA |
| Building Plans Picked Up | 1/4/2022 | APPLICANT |
| Applicant returned to address corrections | 1/30/2024 | MINA HABILI |
| Applicant returned to address corrections | 2/2/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 2/8/2024 | NEHEMIAS RAMOS |
| Applicant returned to address corrections | 2/28/2024 | ALEXANDER JOO |
| Plan Check Approved | 5/2/2024 | ALEXANDER JOO |
| Issued | 5/2/2024 | APPLICANT |
| CofO in Progress | 11/6/2025 | RONNIE MINDANAO |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
| CofO Issued | 11/9/2025 | DEROLD HAUFF |
| Permit Finaled | 11/9/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 6/28/2023 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 2/5/2024 | AMBER CAMPBELL |
| Roof/Waste drainage to street | Cleared | 2/5/2024 | AMBER CAMPBELL |
| Sewer availability | Cleared | 2/5/2024 | AMBER CAMPBELL |
| HPOZ | Cleared | 2/28/2024 | SUKI GERSHENHORN |
Contact Information
| Contractor | Elect Builders; Lic. No.: 1064691-B | 11856 BALBOA BLVD 472 GRANADA HILLS, CA 91344 |
| Engineer | Tan,, Henreik Steven; Lic. No.: C65723 | 5100 LLANO DRIVE WOODLAND HILLS, CA 91364 |
Inspector Information
| RONNIE MINDANAO, (213) 202-3252 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/6/2024 | Corrections Issued | RONNIE MINDANAO |
| METHANE-Subgrade | 6/24/2024 | Corrections Issued | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 6/28/2024 | Approved | RONNIE MINDANAO |
| PLUMBING-Rough | 7/2/2024 | Corrections Issued | RONNIE MINDANAO |
| PLUMBING-Rough | 7/5/2024 | Partial Approval | RONNIE MINDANAO |
| Deputy Methane Barrier | 7/30/2024 | Approved | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 7/30/2024 | Approved | RONNIE MINDANAO |
| Footing/Foundation/Slab | 7/30/2024 | Partial Approval | RONNIE MINDANAO |
| METHANE-Subgrade | 7/30/2024 | Approved | RONNIE MINDANAO |
| Underground Mechanical | 7/30/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| Underground Mechanical | 8/22/2024 | Partial Approval | RONNIE MINDANAO |
| Deputy Drilled-In Anchors | 8/26/2024 | Conditional Approval | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 8/27/2024 | Approved | RONNIE MINDANAO |
| Excavation/Setback/Form/Re-Bar | 8/28/2024 | No Access for Inspection | RONNIE MINDANAO |
| Footing/Foundation/Slab | 8/28/2024 | No Access for Inspection | RONNIE MINDANAO |
| METHANE-Barrier | 8/28/2024 | No Access for Inspection | RONNIE MINDANAO |
| Underground Mechanical | 9/6/2024 | Partial Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 9/25/2024 | Approved | JOSE MACIAS |
| ELECTRICAL-Rough | 10/18/2024 | Corrections Issued | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/18/2024 | Approved | RONNIE MINDANAO |
| Underground Mechanical | 10/18/2024 | Approved | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 11/1/2024 | Conditional Approval | RONNIE MINDANAO |
| Floor/Roof Diaphrgm/Shear Wall | 11/1/2024 | Approved | RONNIE MINDANAO |
| Green Building Rough | 11/1/2024 | Not Ready for Inspection | RONNIE MINDANAO |
| METHANE-Rough | 11/1/2024 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/22/2024 | Approved | RONNIE MINDANAO |
| Rough-Elec/Plmb/HVAC | 12/6/2024 | Not Ready for Inspection | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 12/9/2024 | Corrections Issued | RONNIE MINDANAO |
| Rough-Elec/Plmb/HVAC | 12/11/2024 | Approved | RONNIE MINDANAO |
| BUILDING-Rough-Frame | 12/13/2024 | Approved | RONNIE MINDANAO |
| Green Building Rough | 12/13/2024 | Approved | RONNIE MINDANAO |
| Insulation | 1/13/2025 | Conditional Approval | RONNIE MINDANAO |
| Drywall Nailing | 1/16/2025 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 2/26/2025 | Approved | RONNIE MINDANAO |
| Shower Pan | 2/26/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 9/10/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Final | 9/12/2025 | Corrections Issued | RONNIE MINDANAO |
| Footing/Foundation/Slab | 9/12/2025 | Approved | RONNIE MINDANAO |
| Green Building Final | 9/12/2025 | Approved | RONNIE MINDANAO |
| METHANE-Barrier | 9/12/2025 | Approved | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 9/12/2025 | SGSOV Not Ready | RONNIE MINDANAO |
| Smoke Detectors | 9/12/2025 | Approved | RONNIE MINDANAO |
| Final | 10/9/2025 | Corrections Issued | RONNIE MINDANAO |
| SGSOV-Seismic Gas S/O Valve | 10/9/2025 | SGSOV Approved | RONNIE MINDANAO |
| Final | 10/16/2025 | Partial Approval | RONNIE MINDANAO |
| Final | 11/5/2025 | OK to Issue CofO | RONNIE MINDANAO |