457 N JUNE ST 90004

Certificate Information: 457 N JUNE ST 90004

Application / Permit
21014-20000-06221
Plan Check / Job No.
B21VN17366
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT (E) DETACHED GARAGE WITH STORAGE TO ACCESSORY DWELLING UNIT WITH ADDITION PER STATE LAW
Permit Issued
Issued on 5/2/2024
Issuing Office
Metro
Current Status
CofO Issued on 11/9/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2021 APPLICANT
Assigned to Plan Check Engineer 12/23/2021 JEROME MAGAT PALMA
Corrections Issued 12/25/2021 JEROME MAGAT PALMA
Building Plans Picked Up 1/4/2022 APPLICANT
Applicant returned to address corrections 1/30/2024 MINA HABILI
Applicant returned to address corrections 2/2/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 2/8/2024 NEHEMIAS RAMOS
Applicant returned to address corrections 2/28/2024 ALEXANDER JOO
Plan Check Approved 5/2/2024 ALEXANDER JOO
Issued 5/2/2024 APPLICANT
CofO in Progress 11/6/2025 RONNIE MINDANAO
Permit Finaled 11/9/2025 DEROLD HAUFF
CofO Issued 11/9/2025 DEROLD HAUFF
Permit Finaled 11/9/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 6/28/2023 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 2/5/2024 AMBER CAMPBELL
Roof/Waste drainage to street Cleared 2/5/2024 AMBER CAMPBELL
Sewer availability Cleared 2/5/2024 AMBER CAMPBELL
HPOZ Cleared 2/28/2024 SUKI GERSHENHORN

Contact Information

Contractor Elect Builders; Lic. No.: 1064691-B 11856 BALBOA BLVD 472      GRANADA HILLS, CA 91344
Engineer Tan,, Henreik Steven; Lic. No.: C65723 5100 LLANO DRIVE      WOODLAND HILLS, CA 91364

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2024 Corrections Issued RONNIE MINDANAO
METHANE-Subgrade 6/24/2024 Corrections Issued RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 6/28/2024 Approved RONNIE MINDANAO
PLUMBING-Rough 7/2/2024 Corrections Issued RONNIE MINDANAO
PLUMBING-Rough 7/5/2024 Partial Approval RONNIE MINDANAO
Deputy Methane Barrier 7/30/2024 Approved RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 7/30/2024 Approved RONNIE MINDANAO
Footing/Foundation/Slab 7/30/2024 Partial Approval RONNIE MINDANAO
METHANE-Subgrade 7/30/2024 Approved RONNIE MINDANAO
Underground Mechanical 7/30/2024 Not Ready for Inspection RONNIE MINDANAO
Underground Mechanical 8/22/2024 Partial Approval RONNIE MINDANAO
Deputy Drilled-In Anchors 8/26/2024 Conditional Approval RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 8/27/2024 Approved RONNIE MINDANAO
Excavation/Setback/Form/Re-Bar 8/28/2024 No Access for Inspection RONNIE MINDANAO
Footing/Foundation/Slab 8/28/2024 No Access for Inspection RONNIE MINDANAO
METHANE-Barrier 8/28/2024 No Access for Inspection RONNIE MINDANAO
Underground Mechanical 9/6/2024 Partial Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 9/25/2024 Approved JOSE MACIAS
ELECTRICAL-Rough 10/18/2024 Corrections Issued RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/18/2024 Approved RONNIE MINDANAO
Underground Mechanical 10/18/2024 Approved RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 10/25/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 11/1/2024 Conditional Approval RONNIE MINDANAO
Floor/Roof Diaphrgm/Shear Wall 11/1/2024 Approved RONNIE MINDANAO
Green Building Rough 11/1/2024 Not Ready for Inspection RONNIE MINDANAO
METHANE-Rough 11/1/2024 Approved RONNIE MINDANAO
Interior/Exterior Lathing 11/22/2024 Approved RONNIE MINDANAO
Rough-Elec/Plmb/HVAC 12/6/2024 Not Ready for Inspection ENRIQUE MIRELES
Rough-Elec/Plmb/HVAC 12/9/2024 Corrections Issued RONNIE MINDANAO
Rough-Elec/Plmb/HVAC 12/11/2024 Approved RONNIE MINDANAO
BUILDING-Rough-Frame 12/13/2024 Approved RONNIE MINDANAO
Green Building Rough 12/13/2024 Approved RONNIE MINDANAO
Insulation 1/13/2025 Conditional Approval RONNIE MINDANAO
Drywall Nailing 1/16/2025 Approved RONNIE MINDANAO
Interior/Exterior Lathing 2/26/2025 Approved RONNIE MINDANAO
Shower Pan 2/26/2025 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 9/10/2025 SGSOV Not Ready RONNIE MINDANAO
Final 9/12/2025 Corrections Issued RONNIE MINDANAO
Footing/Foundation/Slab 9/12/2025 Approved RONNIE MINDANAO
Green Building Final 9/12/2025 Approved RONNIE MINDANAO
METHANE-Barrier 9/12/2025 Approved RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 9/12/2025 SGSOV Not Ready RONNIE MINDANAO
Smoke Detectors 9/12/2025 Approved RONNIE MINDANAO
Final 10/9/2025 Corrections Issued RONNIE MINDANAO
SGSOV-Seismic Gas S/O Valve 10/9/2025 SGSOV Approved RONNIE MINDANAO
Final 10/16/2025 Partial Approval RONNIE MINDANAO
Final 11/5/2025 OK to Issue CofO RONNIE MINDANAO