927 W COEUR D'ALENE AVE 90291
Certificate Information: 927 W COEUR D'ALENE AVE 90291
- Application / Permit
- 21014-20000-06218
- Plan Check / Job No.
- B21VN17340
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ADD (8'-6"x 8'-0") 70 SF ENTRY COVERED PORCH AND INTERIOR REMODEL TO (E) TWO-STORY SINGLE FAMILY DWELLING.
- Permit Issued
- Issued on 7/22/2022
- Issuing Office
- Current Status
- CofO Issued on 4/23/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | TROY DEGUZMAN |
| Corrections Issued | 2/4/2022 | TROY DEGUZMAN |
| Quality Review Completed | 2/9/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/10/2022 | APPLICANT |
| Applicant returned to address corrections | 5/18/2022 | TROY DEGUZMAN |
| Plan Check Approved | 6/22/2022 | TROY DEGUZMAN |
| Issued | 7/22/2022 | APPLICANT |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
| CofO Issued | 4/23/2026 | RICHARD STEINBACH |
| Permit Finaled | 4/23/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Miscellaneous | Cleared | 3/10/2022 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 3/10/2022 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 3/10/2022 | STEVEN WECHSLER |
| Miscellaneous | Cleared | 3/10/2022 | STEVEN WECHSLER |
| ZA Case | Cleared | 3/10/2022 | STEVEN WECHSLER |
| ZI | Cleared | 3/10/2022 | STEVEN WECHSLER |
| Address approval | Cleared | 3/15/2022 | DINAH GARIN |
| Roof/Waste drainage to street | Cleared | 3/15/2022 | DINAH GARIN |
| Sewer availability | Cleared | 3/15/2022 | DINAH GARIN |
| Eng Process Fee Ord 176,300 | Cleared | 3/16/2022 | DINAH GARIN |
| Coastal Zone | Cleared | 5/6/2022 | STEVEN WECHSLER |
| Green Code | Cleared | 5/18/2022 | TROY DEGUZMAN |
| Specific Plan | Cleared | 6/2/2022 | VALERIA CEJA |
| Specific Plan | Cleared | 6/3/2022 | IRA BROWN |
| ZI | Cleared | 6/3/2022 | IRA BROWN |
Contact Information
| Architect | Addison,, Susan L; Lic. No.: C25809 | 3456 ASHWOOD AVENUE LOS ANGELES, CA 90066 |
| Architect | Noteware,, Brian Arthur; Lic. No.: C21514 | 845 20TH STREET, #106 SANTA MONICA, CA 90403 |
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 2/28/2024 | No Access for Inspection | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 4/16/2024 | Corrections Issued | HERBERT GIRON |
| PLUMBING-Rough | 4/16/2024 | Partial Approval | HERBERT GIRON |
| Footing/Foundation/Slab | 4/18/2024 | Corrections Issued | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 6/6/2024 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/6/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Rough | 6/6/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| HVAC-Rough | 6/6/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 6/6/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2024 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 8/8/2024 | Not Ready for Inspection | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 8/13/2024 | Not Ready for Inspection | HERBERT GIRON |
| Green Building Rough | 8/13/2024 | Not Ready for Inspection | HERBERT GIRON |
| Deputy Wood Construction | 8/27/2024 | Conditional Approval | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/10/2024 | Corrections Issued | JESUS PINEDA |
| PLUMBING-Rough | 9/10/2024 | Corrections Issued | JESUS PINEDA |
| Floor/Roof Diaphrgm/Shear Wall | 9/12/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 9/12/2024 | Corrections Issued | JESUS PINEDA |
| Interior/Exterior Lathing | 9/30/2024 | Approved | MICHAEL ALLEN |
| BUILDING-Rough-Frame | 10/8/2024 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 10/8/2024 | Approved | JESUS PINEDA |
| Green Building Rough | 10/8/2024 | Approved | JESUS PINEDA |
| PLUMBING-Rough | 10/8/2024 | Approved | JESUS PINEDA |
| Shower Pan | 10/8/2024 | Approved | JESUS PINEDA |
| Special/Order Compliance | 10/8/2024 | Corrections Issued | JESUS PINEDA |
| Insulation | 10/18/2024 | Approved | JESUS PINEDA |
| Drywall Nailing | 10/28/2024 | Approved | JESUS PINEDA |
| Interior/Exterior Lathing | 11/7/2024 | Approved | JESUS PINEDA |
| Final | 1/21/2026 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 1/21/2026 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 1/21/2026 | SGSOV Approved | ANTHONY EGSON |
| Smoke Detectors | 1/21/2026 | Approved | ANTHONY EGSON |
| Final | 2/4/2026 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 4/22/2026 | Conditional Approval | DAVID FEILER |