18254 W SATICOY ST 91335

Certificate Information: 18254 W SATICOY ST 91335

Application / Permit
21014-20000-06216
Plan Check / Job No.
B21VN17338
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 28'-6" X 24'-8" FIRST AND SECOND FLOOR ADDITION TO (E) SINGLE FAMILY DWELLING AND REMOVE PORTION OF FIRST FLOOR ALL WORK PER ENGINEERING NFPA 13D REQUIRED THROUGHOUT "COMPLY WITH DEPARTMENT ORDER effective date 02/21/2020. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
Permit Issued
Issued on 9/29/2022
Issuing Office
Valley
Current Status
CofO Issued on 3/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/15/2021 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 SEWADA ZADOORIAN MILAGARDI
Corrections Issued 1/31/2022 SEWADA ZADOORIAN MILAGARDI
Quality Review Completed 2/15/2022 OMID HEDAYAT
Building Plans Picked Up 2/18/2022 APPLICANT
Applicant returned to address corrections 9/21/2022 SEWADA ZADOORIAN MILAGARDI
Plan Check Approved 9/29/2022 SEWADA ZADOORAN MILAGARDI
Issued 9/29/2022 APPLICANT
CofO in Progress 11/19/2025 ROBERT MINASSIANS
Permit Finaled 3/5/2026 DANIEL SANCHEZ
CofO Issued 3/5/2026 DANIEL SANCHEZ
Permit Finaled 3/5/2026 DANIEL SANCHEZ

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 2/2/2022 CARLOS AGUILERA
Sewer availability Cleared 2/2/2022 CARLOS AGUILERA
Low Impact Development Cleared 7/29/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 8/1/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

ARA SINANIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HASANTHA WEERASEKARA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
SCOTT SHUSTER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOEL GUARDADO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIYA MIHALEVA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOSE RUBIO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID JAMES, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
DAVID HICKMAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN HAMILTON, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
JOHN STEPHENS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
PIERRE VEGA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK VAN SLOOTEN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MICKEY YAMASHITA, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
HAGOP BADOSSIAN, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
KIM BEAUCHAMP, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARK DOVICO, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
THOMAS WOODS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
RAUL VASQUEZ, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
AUGUSTUS ALBAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
LEO MILBAUER, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI
MARIO CUEVAS, (818) 374-9800 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 1/6/2025 Conditional Approval ARAM AVAKIAN
Excavation/Setback/Form/Re-Bar 1/7/2025 Not Ready for Inspection JONATHAN FRANCHINI
Special/Order Compliance 1/7/2025 Not Ready for Inspection JONATHAN FRANCHINI
Special/Order Compliance 1/10/2025 Approved JONATHAN FRANCHINI
BUILDING-Rough-Frame 2/5/2025 Partial Approval JONATHAN FRANCHINI
Sewer 2/5/2025 Approved JONATHAN FRANCHINI
Underground Mechanical 2/5/2025 Approved JONATHAN FRANCHINI
Insulation 2/11/2025 Approved JONATHAN FRANCHINI
Floor/Roof Diaphrgm/Shear Wall 2/19/2025 Approved JONATHAN FRANCHINI
Floor/Roof Diaphrgm/Shear Wall 3/5/2025 Approved PTOLEMY HILL
Pre-Inspection 3/10/2025 Approved PTOLEMY HILL
Insulation 3/17/2025 Corrections Issued JOEL ORDAZ
Deputy Drilled-In Anchors 4/29/2025 Partial Approval JOEL ORDAZ
ELECTRICAL-Rough 4/29/2025 Approved PTOLEMY HILL
Footing/Foundation/Slab 4/29/2025 Approved PTOLEMY HILL
HVAC-Rough 4/29/2025 Approved PTOLEMY HILL
PLUMBING-Rough 4/29/2025 Approved PTOLEMY HILL
Pre-Inspection 4/29/2025 Approved PTOLEMY HILL
Sewer 4/29/2025 Approved PTOLEMY HILL
BUILDING-Rough-Frame 5/22/2025 Approved PTOLEMY HILL
ELECTRICAL-Rough 5/22/2025 Approved PTOLEMY HILL
Green Building Rough 5/22/2025 Approved PTOLEMY HILL
HVAC-Rough 5/22/2025 Approved PTOLEMY HILL
PLUMBING-Rough 5/22/2025 Approved PTOLEMY HILL
Sewer 5/22/2025 Approved PTOLEMY HILL
Wood Frame 5/22/2025 Approved PTOLEMY HILL
Drywall Nailing 5/28/2025 Not Ready for Inspection JONATHAN FRANCHINI
Final 5/28/2025 Not Ready for Inspection JONATHAN FRANCHINI
Green Building Final 5/28/2025 Not Ready for Inspection JONATHAN FRANCHINI
SGSOV-Seismic Gas S/O Valve 5/28/2025 SGSOV Not Ready JONATHAN FRANCHINI
Smoke Detectors 5/28/2025 Not Ready for Inspection JONATHAN FRANCHINI
Insulation 5/29/2025 Approved JONATHAN FRANCHINI
Interior/Exterior Lathing 5/29/2025 Approved JONATHAN FRANCHINI
Drywall Nailing 6/20/2025 Approved JONATHAN FRANCHINI
Final 9/26/2025 Not Ready for Inspection JONATHAN FRANCHINI
Green Building Final 9/26/2025 Not Ready for Inspection JONATHAN FRANCHINI
SGSOV-Seismic Gas S/O Valve 9/26/2025 SGSOV Not Required JONATHAN FRANCHINI
Smoke Detectors 9/26/2025 Approved JONATHAN FRANCHINI
ELECTRICAL-Final 10/17/2025 Approved JONATHAN FRANCHINI
Final 10/17/2025 Corrections Issued JONATHAN FRANCHINI
Green Building Final 10/17/2025 Approved JONATHAN FRANCHINI
HVAC-Final 10/17/2025 Approved JONATHAN FRANCHINI
PLUMBING-Final 10/17/2025 Approved JONATHAN FRANCHINI
Final 11/17/2025 OK to Issue CofO JONATHAN FRANCHINI