7929-7931 N ATOLL AVE 91605
Certificate Information: 7929-7931 N ATOLL AVE 91605
- Application / Permit
- 21014-20000-06209
- Plan Check / Job No.
- B21VN17289
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) TWO STORY ATTACHED 23' X 22'-6" ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e) TO REPLACE (E) CARPORT ALL WORK PER ENGINEERING “The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.”
- Permit Issued
- Issued on 4/21/2022
- Issuing Office
- Current Status
- CofO Issued on 5/18/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/15/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 1/27/2022 | SEWADA ZADOORIAN MILAGARDI |
| Corrections Issued | 1/31/2022 | SEWADA ZADOORIAN MILAGARDI |
| Quality Review Completed | 2/7/2022 | OMID HEDAYAT |
| Building Plans Picked Up | 2/8/2022 | APPLICANT |
| Applicant returned to address corrections | 3/24/2022 | SEWADA ZADOORIAN MILAGARDI |
| Plan Check Approved | 4/7/2022 | SEWADA ZADOORAN MILAGARDI |
| Issued | 4/21/2022 | APPLICANT |
| CofO in Progress | 5/17/2024 | GREGG CUMMINGS |
| Permit Finaled | 5/18/2024 | RUBEN SALAS |
| CofO Issued | 5/18/2024 | RUBEN SALAS |
| Permit Finaled | 5/18/2024 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 3/1/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 3/1/2022 | AMIR KASHFI |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Burnazyan,, Gegam; Lic. No.: C76761 | 5832 JAMIESON AVE ENCINO, CA 91316 |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/21/2022 | Partial Approval | WILLIAM WREN |
| Deputy Drilled-In Anchors | 7/11/2022 | Conditional Approval | DAVID MATSON |
| Footing/Foundation/Slab | 7/21/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/26/2022 | Approved | GREGG CUMMINGS |
| Footing/Foundation/Slab | 7/26/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 9/19/2022 | Approved | WILLIAM WREN |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 11/17/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 11/17/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 11/17/2022 | Corrections Issued | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/8/2022 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 12/8/2022 | Partial Approval | GREGG CUMMINGS |
| PLUMBING-Rough | 12/8/2022 | Partial Approval | GREGG CUMMINGS |
| ELECTRICAL-Rough | 12/22/2022 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 12/22/2022 | Partial Approval | GREGG CUMMINGS |
| HVAC-Rough | 12/22/2022 | Corrections Issued | GREGG CUMMINGS |
| PLUMBING-Rough | 12/22/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Special/Order Compliance | 12/22/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 12/28/2022 | Approved | MICHEL ABAJAN |
| ELECTRICAL-Rough | 12/28/2022 | Approved | MICHEL ABAJAN |
| Green Building Rough | 12/28/2022 | Approved | MICHEL ABAJAN |
| HVAC-Rough | 12/28/2022 | Approved | MICHEL ABAJAN |
| PLUMBING-Rough | 12/28/2022 | Approved | MICHEL ABAJAN |
| Insulation | 1/4/2023 | Corrections Issued | GREGG CUMMINGS |
| Insulation | 1/10/2023 | Approved | GREGG CUMMINGS |
| Drywall Nailing | 1/17/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/17/2023 | Approved | MATTHEW NELSON |
| Shower Pan | 1/17/2023 | Approved | MATTHEW NELSON |
| Interior/Exterior Lathing | 1/24/2023 | Partial Approval | GREGG CUMMINGS |
| Sewer | 4/27/2023 | Approved | GREGG CUMMINGS |
| Final | 4/11/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 4/11/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/11/2024 | SGSOV Not Ready | GREGG CUMMINGS |
| Smoke Detectors | 4/11/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| ELECTRICAL-Final | 4/30/2024 | Approved | GREGG CUMMINGS |
| Final | 4/30/2024 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 4/30/2024 | Approved | GREGG CUMMINGS |
| HVAC-Final | 4/30/2024 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 4/30/2024 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 4/30/2024 | SGSOV Approved | GREGG CUMMINGS |
| Smoke Detectors | 4/30/2024 | Approved | GREGG CUMMINGS |
| Final | 5/16/2024 | OK to Issue CofO | GREGG CUMMINGS |