15446 W ROMAR ST 91345

Certificate Information: 15446 W ROMAR ST 91345

Application / Permit
21014-20000-06208
Plan Check / Job No.
B21VN17288
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
REMOVE (E) ATTACHED PATIO COVER. PROPOSED 9'-6" X 39'-7" ADDITION TO (E) SFD. ALL WORK PER ENGINEERING.
Permit Issued
Issued on 3/28/2022
Issuing Office
Current Status
Issued on 3/28/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/16/2021 APPLICANT
Assigned to Plan Check Engineer 12/23/2021 RAPHAEL ROSAS
Corrections Issued 12/24/2021 RAPHAEL ROSAS
Applicant returned to address corrections 2/23/2022 RAPHAEL ROSAS
Issued 3/28/2022 APPLICANT
Building Plans Picked Up 3/31/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 2/2/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 2/3/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 2/3/2022 JOSE DUARTE-DIAZ
Roof/Waste drainage to street Cleared 3/1/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Zelada,, Mynor Anibal; Lic. No.: C48666 14545 VICTORY BLVD 405      VAN NUYS, CA 91411

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 4/11/2022 Conditional Approval RAUL OLAGI
Excavation/Setback/Form/Re-Bar 4/11/2022 Corrections Issued MICHEL ABAJAN
Footing/Foundation/Slab 4/13/2022 Approved MICHEL ABAJAN
BUILDING-Rough-Frame 4/28/2022 Corrections Issued JENNIFER RABUCHIN
Insulation 4/28/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 5/17/2022 Partial Approval JENNIFER RABUCHIN
Insulation 5/17/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 5/17/2022 Approved JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/3/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 6/10/2022 Not Ready for Inspection JENNIFER RABUCHIN
ELECTRICAL-Rough 6/10/2022 Not Ready for Inspection JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Rough 6/15/2022 Partial Approval JENNIFER RABUCHIN
Interior/Exterior Lathing 6/15/2022 Partial Approval JENNIFER RABUCHIN
PLUMBING-Rough 6/15/2022 Approved JENNIFER RABUCHIN
Insulation 6/21/2022 Approved JENNIFER RABUCHIN
Shower Pan 6/21/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 6/27/2022 Approved MICHAEL SMITH
Interior/Exterior Lathing 7/20/2022 Approved JENNIFER RABUCHIN
Special/Order Compliance 7/20/2022 Corrections Issued JENNIFER RABUCHIN
BUILDING-Rough-Frame 8/10/2022 Approved JENNIFER RABUCHIN
Final 8/10/2022 Corrections Issued JENNIFER RABUCHIN
Green Building Final 8/10/2022 Approved JENNIFER RABUCHIN
Green Building Rough 8/10/2022 Approved JENNIFER RABUCHIN
MERV13>=Final 8/10/2022 Approved JENNIFER RABUCHIN
MERV13>=Rough 8/10/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 8/10/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 8/10/2022 Approved JENNIFER RABUCHIN
ELECTRICAL-Final 8/31/2022 Approved JENNIFER RABUCHIN
Final 8/31/2022 Partial Approval JENNIFER RABUCHIN
HVAC-Final 8/31/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 8/31/2022 Approved JENNIFER RABUCHIN