7059 N ALCOVE AVE 91605

Certificate Information: 7059 N ALCOVE AVE 91605

Application / Permit
21014-20000-06203
Plan Check / Job No.
B21VN17268
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
ADD (31'x 16'-8") ATTACHED REC. ROOM WITH BATHROOM (EXTERIOR ACCESS ONLY)@ REAR TO (E) SINGLE FAMILY DWELLING. WORK PER LA STD WFPP PLAN.
Permit Issued
Issued on 10/11/2022
Issuing Office
Current Status
CofO Issued on 4/23/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/21/2021 APPLICANT
Assigned to Plan Check Engineer 1/27/2022 TROY DEGUZMAN
Corrections Issued 2/1/2022 TROY DEGUZMAN
Quality Review Completed 2/11/2022 OMID HEDAYAT
Building Plans Picked Up 2/15/2022 APPLICANT
Plan Check Approved 10/11/2022 SELLA BENYAMIN
Issued 10/11/2022 APPLICANT
CofO in Progress 9/27/2023 KIRK SANDERS
Permit Finaled 4/23/2024 RUBEN SALAS
CofO Issued 4/23/2024 RUBEN SALAS
Permit Finaled 4/23/2024 RUBEN SALAS

Permit Application Clearance Information

Address approval Cleared 4/14/2022 CARLOS AGUILERA
Sewer availability Cleared 4/14/2022 CARLOS AGUILERA
Eng Process Fee Ord 176,300 Cleared 4/21/2022 CARLOS AGUILERA
Low Impact Development Cleared 9/20/2022 ROGELIO CORTES
Roof/Waste drainage to street Cleared 9/21/2022 CARLOS AGUILERA

Contact Information

Contractor Owner-Builder       ,

Inspector Information

WAYNE REGESTER, (818) 374-1164 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 1/12/2023 Corrections Issued KIRK SANDERS
Footing/Foundation/Slab 1/31/2023 Approved KIRK SANDERS
BUILDING-Rough-Frame 2/7/2023 Partial Approval KIRK SANDERS
Green Building Rough 2/7/2023 Not Ready for Inspection KIRK SANDERS
BUILDING-Rough-Frame 3/2/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Rough 3/2/2023 Corrections Issued KIRK SANDERS
Floor/Roof Diaphrgm/Shear Wall 3/2/2023 Approved KIRK SANDERS
HVAC-Rough 3/2/2023 Corrections Issued KIRK SANDERS
PLUMBING-Rough 3/2/2023 Corrections Issued KIRK SANDERS
BUILDING-Rough-Frame 3/13/2023 Approved KIRK SANDERS
ELECTRICAL-Rough 3/13/2023 Approved KIRK SANDERS
Green Building Rough 3/13/2023 Approved KIRK SANDERS
HVAC-Rough 3/13/2023 Approved KIRK SANDERS
Interior/Exterior Lathing 3/13/2023 Approved KIRK SANDERS
PLUMBING-Rough 3/13/2023 Approved KIRK SANDERS
Insulation 3/23/2023 Approved MISAEL ESPARZA
Interior/Exterior Lathing 3/23/2023 Approved MISAEL ESPARZA
Drywall Nailing 4/3/2023 Approved JUAN VALENZUELA
ELECTRICAL-Final 9/1/2023 Corrections Issued KIRK SANDERS
HVAC-Final 9/1/2023 Corrections Issued KIRK SANDERS
PLUMBING-Final 9/1/2023 Corrections Issued KIRK SANDERS
ELECTRICAL-Final 9/6/2023 Approved KIRK SANDERS
HVAC-Final 9/6/2023 Approved KIRK SANDERS
PLUMBING-Final 9/6/2023 Approved KIRK SANDERS
Final 9/26/2023 OK to Issue CofO KIRK SANDERS
Green Building Final 9/26/2023 Approved KIRK SANDERS
SGSOV-Seismic Gas S/O Valve 9/26/2023 SGSOV Approved KIRK SANDERS
Smoke Detectors 9/26/2023 Approved KIRK SANDERS