12131 W KESWICK ST 91605
Certificate Information: 12131 W KESWICK ST 91605
- Application / Permit
- 21014-20000-06190
- Plan Check / Job No.
- B21VN17234
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- *EPLAN* GROUND FLOOR ADDITION AND ATTACHED PATIO TO (E) SFD WITH ATTAHCED 2-CAR GARAGE. WFPP
- Permit Issued
- Issued on 5/25/2022
- Issuing Office
- Current Status
- CofO Issued on 1/9/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/20/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/21/2021 | VIVIAN LAO |
| Corrections Issued | 12/21/2021 | VIVIAN LAO |
| Applicant returned to address corrections | 2/7/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 2/17/2022 | VIVIAN LAO |
| Applicant returned to address corrections | 2/25/2022 | FARSHAD ALIMOHAMADI |
| Plan Check Approved | 5/24/2022 | VIVIAN LAO |
| Issued | 5/25/2022 | APPLICANT |
| CofO in Progress | 10/31/2024 | MATTHEW NELSON |
| Permit Finaled | 1/9/2025 | RUBEN SALAS |
| CofO Issued | 1/9/2025 | RUBEN SALAS |
| Permit Finaled | 1/9/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 1/24/2022 | LEE GUILBEAUX |
| Sewer availability | Cleared | 1/24/2022 | LEE GUILBEAUX |
| Roof/Waste drainage to street | Cleared | 5/9/2022 | LEE GUILBEAUX |
| Low Impact Development | Cleared | 5/20/2022 | SARAH YOUSSEF |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| WILLIAM WREN, (818) 374-1170 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/1/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Footing/Foundation/Slab | 8/30/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/20/2022 | Corrections Issued | CHRISTOPHER DELLEFIELD |
| Green Building Rough | 9/20/2022 | Approved | CHRISTOPHER DELLEFIELD |
| Floor/Roof Diaphrgm/Shear Wall | 9/22/2022 | Approved | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 9/28/2022 | Partial Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 10/4/2022 | Not Ready for Inspection | CHRISTOPHER DELLEFIELD |
| Deputy Drilled-In Anchors | 10/7/2022 | Conditional Approval | CHRISTOPHER DELLEFIELD |
| BUILDING-Rough-Frame | 10/12/2022 | Approved | DEANDRE HOFFMAN |
| ELECTRICAL-Rough | 10/12/2022 | Approved | DEANDRE HOFFMAN |
| Insulation | 10/26/2022 | Partial Inspection | CHRISTOPHER DELLEFIELD |
| Drywall Nailing | 11/23/2022 | Approved | MATTHEW NELSON |
| Insulation | 11/23/2022 | Approved | MATTHEW NELSON |
| Final | 9/10/2024 | Not Ready for Inspection | MATTHEW NELSON |
| Green Building Final | 9/10/2024 | Corrections Issued | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 9/10/2024 | SGSOV Not Ready | MATTHEW NELSON |
| Smoke Detectors | 9/10/2024 | Approved | MATTHEW NELSON |
| Final | 10/10/2024 | OK to Issue CofO | MATTHEW NELSON |
| Green Building Final | 10/10/2024 | Approved | MATTHEW NELSON |
| SGSOV-Seismic Gas S/O Valve | 10/10/2024 | SGSOV Approved | MATTHEW NELSON |