7452 N WILBUR AVE 91335

Certificate Information: 7452 N WILBUR AVE 91335

Application / Permit
21014-20000-06175
Plan Check / Job No.
B21VN17193
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
562.2 SQ. FT. ADDITION TO AND CONVERT THE (E) 340.3 SQ. FT. STORAGE INTO AN ACCESSORY DWELLING UNIT PER LAMC 12.22 A33(c)-(d).
Permit Issued
Issued on 3/10/2022
Issuing Office
Current Status
CofO Issued on 4/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/10/2021 APPLICANT
Assigned to Plan Check Engineer 12/20/2021 COLIN LOREDO
Corrections Issued 12/25/2021 COLIN LOREDO
Building Plans Picked Up 12/29/2021 APPLICANT
Plan Check Approved 3/8/2022 COLIN LOREDO
Issued 3/10/2022 APPLICANT
CofO in Progress 4/24/2023 JEFFREY BULL
CofO Issued 4/25/2023 MICHAEL SMITH
Permit Finaled 4/25/2023 MICHAEL SMITH

Permit Application Clearance Information

ZA Case Cleared 12/30/2021 DANG NGUYEN
Address approval Cleared 1/14/2022 DAGOVERTO GUERRERO
Eng Process Fee Ord 176,300 Cleared 2/15/2022 DAGOVERTO GUERRERO
Sewer availability Cleared 2/15/2022 DAGOVERTO GUERRERO
Low Impact Development Cleared 3/3/2022 TA ANH
Roof/Waste drainage to street Cleared 3/3/2022 DAGOVERTO GUERRERO

Contact Information

Contractor Owner-Builder       ,

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 5/6/2022 Approved VINCENT HANLEY
PLUMBING-Rough 5/18/2022 Partial Approval VINCENT HANLEY
Sewer 5/18/2022 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 6/3/2022 Conditional Approval KRISTEN CAUSEY
Footing/Foundation/Slab 6/6/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 9/15/2022 Approved JEFFREY BULL
FLOOD-Proofing Certificate 9/15/2022 Approved JEFFREY BULL
Green Building Rough 9/15/2022 Approved JEFFREY BULL
Rough-Elec/Plmb/HVAC 9/15/2022 Approved JEFFREY BULL
Insulation 9/21/2022 Approved MORRIS JACKSON
Interior/Exterior Lathing 9/21/2022 Partial Approval MORRIS JACKSON
Drywall Nailing 10/18/2022 Approved JEFFREY BULL
Shower Pan 10/18/2022 Approved JEFFREY BULL
ELECTRICAL-Final 3/7/2023 Not Ready for Inspection JEFFREY BULL
Final 3/7/2023 Corrections Issued JEFFREY BULL
Green Building Final 3/7/2023 Approved JEFFREY BULL
HVAC-Final 3/7/2023 Approved JEFFREY BULL
PLUMBING-Final 3/7/2023 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 3/7/2023 SGSOV Approved JEFFREY BULL
Smoke Detectors 3/7/2023 Approved JEFFREY BULL
ELECTRICAL-Final 4/24/2023 Approved JEFFREY BULL
Final 4/24/2023 OK to Issue CofO JEFFREY BULL
Service/Power Release 4/24/2023 Approved JEFFREY BULL