8169 N MAMMOTH AVE 91402
Certificate Information: 8169 N MAMMOTH AVE 91402
- Application / Permit
- 21014-20000-06134
- Plan Check / Job No.
- B21VN17093
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- 26'-5" x 43'-0" IRR. SHAPED ADDITION TO AND CONVERT (E) DET. REC. ROOM / STORAGE INTO (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33 (c)-(d) AND ATTACH IT TO (E) CARPORT; ALL WORK PER WFPP
- Permit Issued
- Issued on 4/20/2022
- Issuing Office
- Current Status
- CofO Issued on 4/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/20/2021 | SEAN SHAHMIRI |
| Corrections Issued | 12/21/2021 | SEAN SHAHMIRI |
| Building Plans Picked Up | 12/28/2021 | APPLICANT |
| Plan Check Approved | 4/20/2022 | SEAN SHAHMIRI |
| Issued | 4/20/2022 | APPLICANT |
| CofO in Progress | 2/24/2023 | GREGG CUMMINGS |
| Permit Finaled | 4/5/2023 | DANIEL ORRANTE |
| CofO Issued | 4/5/2023 | DANIEL ORRANTE |
| Permit Finaled | 4/5/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/10/2022 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 3/7/2022 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 3/7/2022 | JOSE DUARTE-DIAZ |
| Construction within easement | Cleared | 3/11/2022 | WALTER RAMIREZ |
| Low Impact Development | Cleared | 4/1/2022 | SUNG JOON WON |
| Roof/Waste drainage to street | Cleared | 4/4/2022 | JOSE DUARTE-DIAZ |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/23/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| Underground Mechanical | 6/23/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 6/29/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| PLUMBING-Rough | 6/29/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/5/2022 | Not Ready for Inspection | WILLIAM WREN |
| PLUMBING-Rough | 7/5/2022 | Partial Approval | WILLIAM WREN |
| Deputy Drilled-In Anchors | 7/13/2022 | Conditional Approval | DAVID MATSON |
| Excavation/Setback/Form/Re-Bar | 7/13/2022 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/18/2022 | Approved | WILLIAM WREN |
| Footing/Foundation/Slab | 7/18/2022 | Approved | WILLIAM WREN |
| ELECTRICAL-Rough | 9/14/2022 | Approved | WILLIAM WREN |
| PLUMBING-Rough | 9/14/2022 | Approved | WILLIAM WREN |
| BUILDING-Rough-Frame | 9/21/2022 | Corrections Issued | GREGG CUMMINGS |
| Final | 9/21/2022 | Corrections Issued | GREGG CUMMINGS |
| Green Building Rough | 9/21/2022 | Not Ready for Inspection | GREGG CUMMINGS |
| HVAC-Rough | 9/21/2022 | Corrections Issued | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/5/2022 | Partial Approval | GREGG CUMMINGS |
| Green Building Rough | 10/5/2022 | Approved | GREGG CUMMINGS |
| HVAC-Rough | 10/5/2022 | Approved | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 10/12/2022 | Partial Approval | GREGG CUMMINGS |
| Insulation | 10/12/2022 | Approved | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/24/2022 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/24/2022 | Partial Approval | GREGG CUMMINGS |
| Underground Mechanical | 10/24/2022 | Partial Approval | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 10/31/2022 | Approved | GREGG CUMMINGS |
| Interior/Exterior Lathing | 10/31/2022 | Partial Approval | GREGG CUMMINGS |
| Shower Pan | 11/7/2022 | Approved | WILLIAM WREN |
| Final | 2/8/2023 | Corrections Issued | GREGG CUMMINGS |
| Green Building Final | 2/8/2023 | Approved | GREGG CUMMINGS |
| SGSOV-Seismic Gas S/O Valve | 2/8/2023 | SGSOV Approved | GREGG CUMMINGS |
| Service/Power Release | 2/8/2023 | Not Ready for Inspection | GREGG CUMMINGS |
| Smoke Detectors | 2/8/2023 | Approved | GREGG CUMMINGS |
| ELECTRICAL-Final | 2/23/2023 | Approved | GREGG CUMMINGS |
| Final | 2/23/2023 | OK to Issue CofO | GREGG CUMMINGS |
| HVAC-Final | 2/23/2023 | Approved | GREGG CUMMINGS |
| PLUMBING-Final | 2/23/2023 | Approved | GREGG CUMMINGS |
| Service/Power Release | 2/23/2023 | Approved | GREGG CUMMINGS |