4355 N LANAI ROAD 91436
Certificate Information: 4355 N LANAI ROAD 91436
- Application / Permit
- 21014-20000-06118
- Plan Check / Job No.
- B21VN17049
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- ENCLOSE (E) BREEZEWAY, ADD NEW FRONT PORCH (38 SF) AND TWO NEW ADDITIONS AT REAR (211 SF AND 42.5 SF) AND INTERIOR REMODEL; ALL WORK PER ENGINEERING DESIGN
- Permit Issued
- Issued on 3/22/2022
- Issuing Office
- Current Status
- CofO Issued on 11/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/23/2021 | SEAN SHAHMIRI |
| Corrections Issued | 12/28/2021 | SEAN SHAHMIRI |
| Quality Review Completed | 12/29/2021 | OMID HEDAYAT |
| Building Plans Picked Up | 1/3/2022 | APPLICANT |
| Applicant returned to address corrections | 3/15/2022 | SEAN SHAHMIRI |
| Plan Check Approved | 3/17/2022 | SEAN SHAHMIRI |
| Issued | 3/22/2022 | APPLICANT |
| CofO in Progress | 11/13/2023 | VINCENT HANLEY |
| CofO Issued | 11/13/2023 | JOHN JANSON |
| Permit Finaled | 11/13/2023 | JOHN JANSON |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 1/14/2022 | AMIR KASHFI |
| Sewer availability | Cleared | 1/14/2022 | AMIR KASHFI |
| Eng Process Fee Ord 176,300 | Cleared | 1/18/2022 | AMIR KASHFI |
| Grading Pre-Inspection | Cleared | 1/18/2022 | ALEXANDER ANDREWS |
| ZA Case | Cleared | 1/25/2022 | PABLO ESTRADA |
| Hydrant and Access approval | Cleared | 3/2/2022 | CINDY JOSSELYN |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Markarian,, Mardiros; Lic. No.: C53434 | 3814 VANALDEN AVE TARZANA, CA 91356 |
Inspector Information
| THOMAS FINNILA, (818) 774-4324 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/6/2022 | Approved | SEAN HAUPT |
| Footing/Foundation/Slab | 4/6/2022 | Approved | SEAN HAUPT |
| Deputy Wood Construction | 4/14/2022 | Conditional Approval | KRISTEN CAUSEY |
| ELECTRICAL-Rough | 5/9/2022 | Approved | VINCENT HANLEY |
| HVAC-Rough | 5/9/2022 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Rough | 5/9/2022 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/26/2022 | Partial Approval | ROBERT GOLD |
| Green Building Rough | 5/26/2022 | Not Ready for Inspection | ROBERT GOLD |
| HVAC-Rough | 5/26/2022 | Approved | ROBERT GOLD |
| BUILDING-Rough-Frame | 6/1/2022 | Corrections Issued | HENRY KIM |
| Interior/Exterior Lathing | 6/1/2022 | Not Ready for Inspection | HENRY KIM |
| Pre-Inspection | 6/1/2022 | Approved | HENRY KIM |
| BUILDING-Rough-Frame | 6/6/2022 | Corrections Issued | HENRY KIM |
| Green Building Rough | 6/6/2022 | Corrections Issued | HENRY KIM |
| Insulation | 6/6/2022 | Partial Inspection | HENRY KIM |
| BUILDING-Rough-Frame | 6/7/2022 | Corrections Issued | HENRY KIM |
| Green Building Rough | 6/7/2022 | Approved | HENRY KIM |
| Insulation | 6/7/2022 | Approved | HENRY KIM |
| Interior/Exterior Lathing | 6/7/2022 | Partial Approval | HENRY KIM |
| Interior/Exterior Lathing | 6/10/2022 | Partial Inspection | JESUS PINEDA |
| Drywall Nailing | 6/15/2022 | Approved | MORRIS JACKSON |
| Interior/Exterior Lathing | 6/15/2022 | Approved | MORRIS JACKSON |
| BUILDING-Rough-Frame | 10/26/2023 | Approved | SEAN WIRCH |
| Final | 10/26/2023 | Partial Approval | SEAN WIRCH |
| Green Building Final | 10/26/2023 | Approved | SEAN WIRCH |
| SGSOV-Seismic Gas S/O Valve | 10/26/2023 | SGSOV Approved | SEAN WIRCH |
| Smoke Detectors | 10/26/2023 | Approved | SEAN WIRCH |
| Final | 11/13/2023 | OK to Issue CofO | VINCENT HANLEY |