17311 W DEARBORN ST 91325
Certificate Information: 17311 W DEARBORN ST 91325
- Application / Permit
- 21014-20000-06103
- Plan Check / Job No.
- B21VN16980
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT 23' X 10' IRR.-SHAPE PORTION OF ATTACHED BREEZEWAY TO HABITABLE SPACE W/ 2' X 10" COVERED PORCH ADDITION TO FRONT OF (E) SFD. ALL WORK DONE PER ENGINEERING.
- Permit Issued
- Issued on 4/28/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/6/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | GURUNATH NESARAJAH |
| Corrections Issued | 12/17/2021 | GURUNATH NESARAJAH |
| Plan Check Approved | 1/24/2022 | GURUNATH NESARAJAH |
| Building Plans Picked Up | 1/24/2022 | APPLICANT |
| Issued | 4/28/2022 | APPLICANT |
| CofO in Progress | 2/28/2023 | JAVIER RAMOS JR |
| Permit Finaled | 3/6/2023 | MICHAEL SMITH |
| CofO Issued | 3/6/2023 | MICHAEL SMITH |
| Permit Finaled | 3/6/2023 | MICHAEL SMITH |
Permit Application Clearance Information
| Roof/Waste drainage to street | Cleared | 12/23/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | JOSE DUARTE-DIAZ |
| ZA Case | Cleared | 12/30/2021 | DANG NGUYEN |
| ZI | Cleared | 12/30/2021 | DANG NGUYEN |
Contact Information
| Contractor | Ferguson Construction And Fine Cabinetry; Lic. No.: 787034-B | 6300 AGNES AVENUE NORTH HOLLYWOOD, CA 91606 |
| Engineer | Reith,, David Lee; Lic. No.: C72122 | 1319 FEATHER AVE THOUSAND OAKS, CA 91360 |
Inspector Information
| CHRISTOPHER ROJAS, (818) 374-1160 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 6/8/2022 | Conditional Approval | JAVIER RAMOS JR |
| Deputy Drilled-In Anchors | 6/9/2022 | Conditional Approval | JAVIER RAMOS JR |
| Footing/Foundation/Slab | 6/17/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 7/15/2022 | Partial Approval | DEANDRE HOFFMAN |
| Deputy Drilled-In Anchors | 8/16/2022 | Conditional Approval | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 9/13/2022 | Partial Approval | JAVIER RAMOS JR |
| ELECTRICAL-Rough | 9/13/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/13/2022 | Partial Approval | JAVIER RAMOS JR |
| PLUMBING-Rough | 9/13/2022 | Approved | JAVIER RAMOS JR |
| Floor/Roof Diaphrgm/Shear Wall | 9/20/2022 | Approved | JAVIER RAMOS JR |
| Green Building Rough | 9/29/2022 | Approved | JAVIER RAMOS JR |
| Insulation | 9/29/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 9/29/2022 | Partial Approval | JAVIER RAMOS JR |
| Drywall Nailing | 10/6/2022 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 10/27/2022 | Not Ready for Inspection | JAVIER RAMOS JR |
| Shower Pan | 10/27/2022 | Approved | JAVIER RAMOS JR |
| BUILDING-Rough-Frame | 1/3/2023 | Approved | JAVIER RAMOS JR |
| Final | 1/3/2023 | Corrections Issued | JAVIER RAMOS JR |
| Green Building Final | 1/3/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| HVAC-Rough | 1/3/2023 | Approved | JAVIER RAMOS JR |
| Interior/Exterior Lathing | 1/3/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 1/3/2023 | SGSOV Not Ready | JAVIER RAMOS JR |
| Smoke Detectors | 1/3/2023 | Not Ready for Inspection | JAVIER RAMOS JR |
| Final | 2/9/2023 | OK to Issue CofO | JAVIER RAMOS JR |
| Green Building Final | 2/9/2023 | Approved | JAVIER RAMOS JR |
| SGSOV-Seismic Gas S/O Valve | 2/9/2023 | SGSOV Approved | JAVIER RAMOS JR |
| Smoke Detectors | 2/9/2023 | Approved | JAVIER RAMOS JR |