18622 W SATICOY ST 91335

Certificate Information: 18622 W SATICOY ST 91335

Application / Permit
21014-20000-06102
Plan Check / Job No.
B21VN16978
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
PROPOSED 12'-10" x 19'-5" ADDITION TO THE (E) SINGLE FAMILY DWELLING FOR A NEW MASTER BEDROOM AND A BATHROOM AND 6'-1" x 7'-11" ADDITION FOR A NEW BATHROOM.
Permit Issued
Issued on 4/21/2022
Issuing Office
Current Status
CofO Issued on 10/4/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/8/2021 APPLICANT
Assigned to Plan Check Engineer 12/9/2021 SARKIS HARABEDIAN
Corrections Issued 12/9/2021 SARKIS HARABEDIAN
Applicant returned to address corrections 1/15/2022 SARKIS HARABEDIAN
Building Plans Picked Up 1/18/2022 APPLICANT
Plan Check Approved 3/13/2022 SARKIS HARABEDIAN
Issued 4/21/2022 APPLICANT
CofO in Progress 10/4/2022 JEFFREY BULL
CofO Issued 10/4/2022 MICHAEL SMITH
Permit Finaled 10/4/2022 MICHAEL SMITH

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 1/5/2022 JOSE DUARTE-DIAZ
Sewer availability Cleared 1/5/2022 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 1/6/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor A C Pros Inc; Lic. No.: 871281-B 18653 VENTURA BLVD #251      TARZANA, CA 91356
Engineer Levin,, Vladimir; Lic. No.: C35001 11606 CHENAULT STR, UNIT 301      LOS ANGELES, CA 90049

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/22/2022 Approved VINCENT HANLEY
Footing/Foundation/Slab 4/22/2022 Approved VINCENT HANLEY
Deputy Drilled-In Anchors 4/28/2022 Approved VINCENT HANLEY
BUILDING-Rough-Frame 5/9/2022 Partial Approval VINCENT HANLEY
Green Building Rough 5/9/2022 Not Ready for Inspection VINCENT HANLEY
Insulation 5/9/2022 Partial Approval VINCENT HANLEY
PLUMBING-Rough 5/9/2022 Partial Approval VINCENT HANLEY
Floor/Roof Diaphrgm/Shear Wall 5/12/2022 Partial Approval VINCENT HANLEY
Wood Frame 5/12/2022 Partial Approval VINCENT HANLEY
ELECTRICAL-Rough 5/19/2022 Approved JUSTIN HAWLEY
HVAC-Rough 5/19/2022 Approved JUSTIN HAWLEY
PLUMBING-Rough 5/19/2022 Approved JUSTIN HAWLEY
Wood Frame 5/19/2022 Approved JUSTIN HAWLEY
Drywall Nailing 5/26/2022 Approved VINCENT HANLEY
Insulation 5/26/2022 Approved VINCENT HANLEY
Interior/Exterior Lathing 5/26/2022 Partial Approval VINCENT HANLEY
Interior/Exterior Lathing 6/14/2022 Approved JEFFREY BULL
BUILDING-Rough-Frame 7/12/2022 Approved JEFFREY BULL
Final 7/12/2022 OK to Issue CofO JEFFREY BULL
Green Building Final 7/12/2022 Approved JEFFREY BULL
Green Building Rough 7/12/2022 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 7/12/2022 SGSOV Approved JEFFREY BULL
Smoke Detectors 7/12/2022 Approved JEFFREY BULL