18038 W BLUE SAIL DR 90272
Certificate Information: 18038 W BLUE SAIL DR 90272
- Application / Permit
- 21014-20000-06097
- Plan Check / Job No.
- B21VN16961
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- 6'-4" X 24'-9" ADDITION OF A NEW ENTRY, LAUNDRY AND EQUIPT. ROOM TO THE (E) SFD.
- Permit Issued
- Issued on 7/12/2022
- Issuing Office
- Current Status
- CofO Issued on 10/25/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2021 | SERGIO MUNIZ |
| Corrections Issued | 12/18/2021 | SERGIO MUNIZ |
| Plan Check Approved | 7/1/2022 | SERGIO MUNIZ |
| Building Plans Picked Up | 7/11/2022 | APPLICANT |
| Issued | 7/12/2022 | APPLICANT |
| CofO in Progress | 10/4/2023 | ARAM AVEDISIAN |
| Permit Finaled | 10/25/2023 | DANIEL ORRANTE |
| CofO Issued | 10/25/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/25/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2022 | ANTHONY MAINEZ |
| Roof/Waste drainage to street | Cleared | 2/8/2022 | ANTHONY MAINEZ |
| Grading Pre-Inspection | Cleared | 3/21/2022 | PATRICK MISCHLICH |
| Coastal Zone | Cleared | 5/31/2022 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 5/31/2022 | MIGUEL GAMBOA |
| Miscellaneous | Cleared | 5/31/2022 | MIGUEL GAMBOA |
Contact Information
| Contractor | B C Construction; Lic. No.: 676747-B | 1137 EAST 46TH STREET LONG BEACH, CA 90807 |
| Engineer | Kessler,, Dale Edward; Lic. No.: C58524 | 16043 HART ST VAN NUYS, CA 91406 |
Inspector Information
| DANIEL VERA, (213) 577-9924 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 7/14/2022 | Approved | ANDREW NAVE |
| Underground Mechanical | 7/14/2022 | Approved | ANDREW NAVE |
| Rough-Elec/Plmb/HVAC | 9/19/2022 | Corrections Issued | BRENDAN LOONEY |
| Wood Frame | 9/19/2022 | Corrections Issued | BRENDAN LOONEY |
| BUILDING-Rough-Frame | 11/1/2022 | Approved | BRENDAN LOONEY |
| ELECTRICAL-Rough | 11/1/2022 | Approved | BRENDAN LOONEY |
| Green Building Rough | 11/1/2022 | Approved | BRENDAN LOONEY |
| HVAC-Rough | 11/1/2022 | Approved | BRENDAN LOONEY |
| PLUMBING-Rough | 11/1/2022 | Approved | BRENDAN LOONEY |
| Drywall Nailing | 11/15/2022 | Approved | BRENDAN LOONEY |
| Interior/Exterior Lathing | 11/15/2022 | Partial Approval | BRENDAN LOONEY |
| Final | 9/25/2023 | Corrections Issued | ARAM AVEDISIAN |
| Green Building Final | 9/25/2023 | Approved | ARAM AVEDISIAN |
| SGSOV-Seismic Gas S/O Valve | 9/25/2023 | SGSOV Approved | ARAM AVEDISIAN |
| Smoke Detectors | 9/25/2023 | Approved | ARAM AVEDISIAN |
| Final | 9/29/2023 | Corrections Issued | EVAN COOPER |
| Final | 10/4/2023 | OK to Issue CofO | ARAM AVEDISIAN |