2833 1/2 S BUCKINGHAM ROAD 90016

Certificate Information: 2833 1/2 S BUCKINGHAM ROAD 90016

Application / Permit
21014-20000-06095
Plan Check / Job No.
B21VN16958
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
4' X 20' AND 11' X 12' ADDITIONS TO AND CONVERT THE (E) 400 SQ. FT. GARAGE INTO A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (d). ALL WORK PER WFPP 2020.
Permit Issued
Issued on 6/3/2022
Issuing Office
Current Status
Issued on 6/3/2022
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 12/7/2021 APPLICANT
Assigned to Plan Check Engineer 12/15/2021 OMAR GARNICA
Corrections Issued 12/18/2021 OMAR GARNICA
Applicant returned to address corrections 3/24/2022 OMAR GARNICA
Plan Check Approved 5/23/2022 OMAR GARNICA
Building Plans Picked Up 5/23/2022 APPLICANT
Issued 6/3/2022 APPLICANT

Permit Application Clearance Information

Address approval Cleared 12/29/2021 AMAAN MALIK
Roof/Waste drainage to street Cleared 12/29/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 1/3/2022 AMAAN MALIK
Sewer availability Cleared 1/3/2022 AMAAN MALIK

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 6/8/2022 Approved STUART CHAPMAN
Deputy Drilled-In Anchors 6/9/2022 Approved STUART CHAPMAN
ELECTRICAL-Rough 6/27/2022 No Access for Inspection JEFFREY MEAD
PLUMBING-Rough 6/27/2022 No Access for Inspection JEFFREY MEAD
Wood Frame 6/27/2022 No Access for Inspection JEFFREY MEAD
ELECTRICAL-Rough 7/5/2022 Approved STUART CHAPMAN
PLUMBING-Rough 7/5/2022 Approved STUART CHAPMAN
Wood Frame 7/5/2022 Partial Approval STUART CHAPMAN
BUILDING-Rough-Frame 7/18/2022 Approved STUART CHAPMAN
HVAC-Rough 7/18/2022 Corrections Issued STUART CHAPMAN
Interior/Exterior Lathing 7/18/2022 Partial Approval STUART CHAPMAN
Insulation 7/20/2022 Corrections Issued STUART CHAPMAN
BUILDING-Rough-Frame 8/4/2022 Conditional Approval STUART CHAPMAN
Green Building Rough 8/4/2022 Approved STUART CHAPMAN
HVAC-Rough 8/4/2022 Approved STUART CHAPMAN
Insulation 8/4/2022 Approved STUART CHAPMAN
Drywall Nailing 8/11/2022 Approved STUART CHAPMAN
BUILDING-Rough-Frame 10/31/2022 Approved STUART CHAPMAN
Final 10/31/2022 Not Ready for Inspection STUART CHAPMAN
Footing/Foundation/Slab 10/31/2022 Approved STUART CHAPMAN
Green Building Final 10/31/2022 Not Ready for Inspection STUART CHAPMAN
SGSOV-Seismic Gas S/O Valve 10/31/2022 SGSOV Not Ready STUART CHAPMAN
Sewer 10/31/2022 Approved STUART CHAPMAN
Smoke Detectors 10/31/2022 Not Ready for Inspection STUART CHAPMAN
Underground Mechanical 10/31/2022 Partial Approval STUART CHAPMAN
Final 5/26/2023 Not Ready for Inspection CALEB MEISTER
Green Building Final 5/26/2023 Not Ready for Inspection CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 5/26/2023 SGSOV Not Ready CALEB MEISTER
Smoke Detectors 5/26/2023 Not Ready for Inspection CALEB MEISTER