19960 W COVELLO ST 91306
Certificate Information: 19960 W COVELLO ST 91306
- Application / Permit
- 21014-20000-06089
- Plan Check / Job No.
- B21VN16944
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- PROPOSED 14'X10' CLOSET AND BATHRM ADDITION TO EX BEDRM AT REAR. ALL WORK PER WFPP.
- Permit Issued
- Issued on 1/21/2022
- Issuing Office
- Current Status
- CofO Issued on 7/22/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/10/2021 | HAYATO TSUCHIYA |
| Corrections Issued | 12/10/2021 | HAYATO TSUCHIYA |
| Plan Check Approved | 1/18/2022 | HAYATO TSUCHIYA |
| Issued | 1/21/2022 | APPLICANT |
| Building Plans Picked Up | 1/26/2022 | APPLICANT |
| CofO in Progress | 7/19/2022 | STEVEN BACK |
| Permit Finaled | 7/22/2022 | JOHN JANSON |
| CofO Issued | 7/22/2022 | JOHN JANSON |
| Permit Finaled | 7/22/2022 | JOHN JANSON |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | CARLOS AGUILERA |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 2/3/2022 | Approved | STEVEN BACK |
| Footing/Foundation/Slab | 2/3/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 2/10/2022 | Partial Approval | STEVEN BACK |
| PLUMBING-Rough | 2/10/2022 | Partial Approval | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2022 | Partial Approval | STEVEN BACK |
| Insulation | 2/15/2022 | Order to Comply Issued | STEVEN BACK |
| ELECTRICAL-Rough | 3/1/2022 | Approved | STEVEN BACK |
| Floor/Roof Diaphrgm/Shear Wall | 3/1/2022 | Approved | STEVEN BACK |
| HVAC-Rough | 3/1/2022 | Approved | STEVEN BACK |
| PLUMBING-Rough | 3/1/2022 | Approved | STEVEN BACK |
| BUILDING-Rough-Frame | 3/7/2022 | Approved | STEVEN BACK |
| Green Building Rough | 3/7/2022 | Approved | STEVEN BACK |
| Interior/Exterior Lathing | 3/7/2022 | Approved | STEVEN BACK |
| Shower Pan | 3/7/2022 | Approved | STEVEN BACK |
| Drywall Nailing | 3/11/2022 | Approved | JESUS PINEDA |
| Final | 7/19/2022 | OK to Issue CofO | STEVEN BACK |
| Green Building Final | 7/19/2022 | Approved | STEVEN BACK |
| SGSOV-Seismic Gas S/O Valve | 7/19/2022 | SGSOV Approved | STEVEN BACK |
| Smoke Detectors | 7/19/2022 | Approved | STEVEN BACK |