19958 W COVELLO ST 91306
Certificate Information: 19958 W COVELLO ST 91306
- Application / Permit
- 21014-20000-06088
- Plan Check / Job No.
- B21VN16939
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 18' X 24' ADDITION TO AND CONVERT THE (E) 18' X 20' DETACHED GARAGE INTO A (N) ACCESSORY DWELLING UNIT AS PER LAMC 12.22.A.33 (C) AND (D) , ALL WORK PER WFPP
- Permit Issued
- Issued on 10/14/2022
- Issuing Office
- Valley
- Current Status
- CofO Issued on 3/6/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/16/2021 | RARES BODEA |
| Corrections Issued | 12/21/2021 | RARES BODEA |
| Building Plans Picked Up | 12/28/2021 | APPLICANT |
| Applicant returned to address corrections | 8/23/2022 | ALEC MOUSAKHANIAN |
| Applicant returned to address corrections | 9/19/2022 | JESSE ARELLANO |
| Issued | 10/14/2022 | APPLICANT |
| CofO in Progress | 12/8/2023 | ALEXANDER HANDY |
| Permit Finaled | 3/6/2024 | JOHN JANSON |
| CofO Issued | 3/6/2024 | JOHN JANSON |
| Permit Finaled | 3/6/2024 | JOHN JANSON |
Permit Application Clearance Information
| Address approval | Cleared | 1/5/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 1/6/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 1/6/2022 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 3/15/2022 | RIDWAN HARDY |
| Construction within easement | Cleared | 3/15/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 7/29/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 8/22/2022 | CARLOS AGUILERA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID FASTIGGI, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
| ALEXANDER HANDY, (818) 774-4317 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Drilled-In Anchors | 2/16/2023 | Conditional Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 3/20/2023 | Partial Approval | ALEXANDER HANDY |
| Sewer | 3/20/2023 | Approved | ALEXANDER HANDY |
| Underground Mechanical | 3/20/2023 | Approved | ALEXANDER HANDY |
| Footing/Foundation/Slab | 3/29/2023 | Approved | HORACE FULTZ |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 6/12/2023 | Partial Approval | ALEXANDER HANDY |
| ELECTRICAL-Rough | 6/12/2023 | Approved | ALEXANDER HANDY |
| Green Building Rough | 6/12/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 6/12/2023 | Partial Approval | ALEXANDER HANDY |
| PLUMBING-Rough | 6/12/2023 | Approved | ALEXANDER HANDY |
| BUILDING-Rough-Frame | 6/14/2023 | Approved | ALEXANDER HANDY |
| Insulation | 6/14/2023 | Approved | ALEXANDER HANDY |
| Drywall Nailing | 6/20/2023 | Approved | ALEXANDER HANDY |
| Interior/Exterior Lathing | 6/20/2023 | Approved | ALEXANDER HANDY |
| Final | 12/5/2023 | Corrections Issued | ALEXANDER HANDY |
| Green Building Final | 12/5/2023 | Approved | ALEXANDER HANDY |
| SGSOV-Seismic Gas S/O Valve | 12/5/2023 | SGSOV Approved | ALEXANDER HANDY |
| Service/Power Release | 12/5/2023 | Approved | ALEXANDER HANDY |
| Smoke Detectors | 12/5/2023 | Approved | ALEXANDER HANDY |
| Final | 12/7/2023 | OK to Issue CofO | ALEXANDER HANDY |