ADDITION TO DETACHED GARAGE AND Convert into new ADU
Permit Issued
Issued on 7/14/2022
Issuing Office
Current Status
CofO Issued on 5/3/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 1/11/2022 APPLICANT
Assigned to Plan Check Engineer 1/12/2022 JOE VO
Corrections Issued 1/13/2022 JOE VO
Plan Check Approved 7/1/2022 JOE VO
Issued 7/14/2022 APPLICANT
CofO in Progress 5/2/2023 MARIO CUEVAS
Permit Finaled 5/3/2023 BRUCE TODD
CofO Issued 5/3/2023 BRUCE TODD
Permit Finaled 5/3/2023 BRUCE TODD

Permit Application Clearance Information

Address approval Cleared 3/14/2022 TREVOR QUAN
Roof/Waste drainage to street Cleared 3/14/2022 TREVOR QUAN
Eng Process Fee Ord 176,300 Cleared 3/15/2022 TREVOR QUAN
Sewer availability Cleared 3/15/2022 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JEREMY TODD, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
MARVIN FONSECA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI
DANIEL GUEVARA, (213) 978-4495 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/12/2022 Approved MARIO CUEVAS
Footing/Foundation/Slab 8/22/2022 Corrections Issued MARIO CUEVAS
PLUMBING-Rough 8/30/2022 Partial Approval MARIO CUEVAS
Footing/Foundation/Slab 9/9/2022 Partial Inspection MARIO CUEVAS
Footing/Foundation/Slab 9/20/2022 Corrections Issued MARIO CUEVAS
Footing/Foundation/Slab 9/21/2022 Approved MARIO CUEVAS
BUILDING-Rough-Frame 10/19/2022 Corrections Issued MARIO CUEVAS
Floor/Roof Diaphrgm/Shear Wall 10/19/2022 Approved MARIO CUEVAS
Green Building Rough 10/19/2022 Not Ready for Inspection MARIO CUEVAS
BUILDING-Rough-Frame 10/25/2022 Approved MARIO CUEVAS
ELECTRICAL-Rough 10/25/2022 Approved MARIO CUEVAS
Green Building Rough 10/25/2022 Approved MARIO CUEVAS
Insulation 10/28/2022 Approved MARIO CUEVAS
PLUMBING-Rough 10/28/2022 Approved MARIO CUEVAS
Drywall Nailing 11/1/2022 Approved MARIO CUEVAS
Interior/Exterior Lathing 11/1/2022 Approved MARIO CUEVAS
Final 2/6/2023 Not Ready for Inspection MARIO CUEVAS
Green Building Final 2/6/2023 Not Ready for Inspection MARIO CUEVAS
SGSOV-Seismic Gas S/O Valve 2/6/2023 SGSOV Not Ready MARIO CUEVAS
Smoke Detectors 2/6/2023 Not Ready for Inspection MARIO CUEVAS
Final 2/22/2023 Corrections Issued MARIO CUEVAS
Green Building Final 2/22/2023 Approved MARIO CUEVAS
SGSOV-Seismic Gas S/O Valve 2/22/2023 SGSOV Approved MARIO CUEVAS
Smoke Detectors 2/22/2023 Approved MARIO CUEVAS
Final 2/23/2023 Conditional Approval MARIO CUEVAS