14653 W COHASSET ST 91405
Certificate Information: 14653 W COHASSET ST 91405
- Application / Permit
- 21014-20000-06079
- Plan Check / Job No.
- B21VN16873
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT 18'-5" X 20'-7" DETACHED GARAGE AND ADD 14'-5" X 18'-5" TO CREATE A (N) ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) AND (d). ALL WORK PER ENGINEERING. "COMPLY WITH DEPARTMENT ORDER effective date 11/08/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE"
- Permit Issued
- Issued on 5/2/2022
- Issuing Office
- Current Status
- CofO Issued on 5/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 12/7/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/15/2021 | RAPHAEL ROSAS |
| Corrections Issued | 12/16/2021 | RAPHAEL ROSAS |
| Applicant returned to address corrections | 4/11/2022 | RAPHAEL ROSAS |
| Plan Check Approved | 4/21/2022 | RAPHAEL ROSAS |
| Building Plans Picked Up | 4/22/2022 | APPLICANT |
| Issued | 5/2/2022 | APPLICANT |
| CofO in Progress | 1/3/2023 | THOMAS WOODS |
| Permit Finaled | 5/21/2023 | DAVID JAMES |
| CofO Issued | 5/21/2023 | DAVID JAMES |
| Permit Finaled | 5/21/2023 | DAVID JAMES |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2021 | JOSE DUARTE-DIAZ |
| Eng Process Fee Ord 176,300 | Cleared | 12/20/2021 | JOSE DUARTE-DIAZ |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | JOSE DUARTE-DIAZ |
| Sewer availability | Cleared | 12/30/2021 | ABDULLAH SADOZAI |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Khatchadourian,, Vicken; Lic. No.: S3141 | 1221 N CEDAR ST GLENDALE, CA 92107 |
Inspector Information
| ARA SINANIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HASANTHA WEERASEKARA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| SCOTT SHUSTER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOEL GUARDADO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARIYA MIHALEVA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOSE RUBIO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID JAMES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| DAVID HICKMAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN HAMILTON, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| JOHN STEPHENS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| PIERRE VEGA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK VAN SLOOTEN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MICKEY YAMASHITA, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RICHARD ROBLES, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| HAGOP BADOSSIAN, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| KIM BEAUCHAMP, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| MARK DOVICO, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| THOMAS WOODS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| RAUL VASQUEZ, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| AUGUSTUS ALBAS, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| FELIPE PENICHE, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
| LEO MILBAUER, (818) 374-9800 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 5/6/2022 | No Access for Inspection | THOMAS WOODS |
| PLUMBING-Rough | 7/8/2022 | Corrections Issued | MICKEY YAMASHITA |
| Pre-Inspection | 7/8/2022 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 7/11/2022 | Corrections Issued | MICKEY YAMASHITA |
| Gas Test | 7/11/2022 | Corrections Issued | MICKEY YAMASHITA |
| PLUMBING-Rough | 7/11/2022 | Corrections Issued | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 7/19/2022 | Corrections Issued | THOMAS WOODS |
| Underground Mechanical | 7/19/2022 | Not Ready for Inspection | MICKEY YAMASHITA |
| Footing/Foundation/Slab | 7/29/2022 | Corrections Issued | KIM BEAUCHAMP |
| Gas Test | 7/29/2022 | Not Ready for Inspection | KIM BEAUCHAMP |
| PLUMBING-Rough | 7/29/2022 | Corrections Issued | KIM BEAUCHAMP |
| ELECTRICAL-Rough | 8/2/2022 | Corrections Issued | THOMAS WOODS |
| Footing/Foundation/Slab | 8/2/2022 | Corrections Issued | THOMAS WOODS |
| Gas Test | 8/2/2022 | Approved | THOMAS WOODS |
| PLUMBING-Rough | 8/2/2022 | Corrections Issued | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 8/2/2022 | SGSOV Approved | THOMAS WOODS |
| Sewer | 8/2/2022 | Corrections Issued | THOMAS WOODS |
| ELECTRICAL-Rough | 8/10/2022 | Not Ready for Inspection | THOMAS WOODS |
| Footing/Foundation/Slab | 8/10/2022 | Approved | THOMAS WOODS |
| Gas Test | 8/10/2022 | Approved | THOMAS WOODS |
| PLUMBING-Rough | 8/10/2022 | Approved | THOMAS WOODS |
| Sewer | 8/10/2022 | Approved | THOMAS WOODS |
| Shower Pan | 8/16/2022 | Approved | THOMAS WOODS |
| Wood Frame | 9/14/2022 | Approved | THOMAS WOODS |
| ELECTRICAL-Rough | 9/19/2022 | Approved | THOMAS WOODS |
| Interior/Exterior Lathing | 9/19/2022 | Partial Approval | THOMAS WOODS |
| Interior/Exterior Lathing | 9/21/2022 | Approved | THOMAS WOODS |
| Drywall Nailing | 10/5/2022 | Approved | THOMAS WOODS |
| BUILDING-Rough-Frame | 1/3/2023 | Approved | THOMAS WOODS |
| ELECTRICAL-Final | 1/3/2023 | Approved | THOMAS WOODS |
| Final | 1/3/2023 | OK to Issue CofO | THOMAS WOODS |
| Gas Test | 1/3/2023 | Approved | THOMAS WOODS |
| Green Building Final | 1/3/2023 | Approved | THOMAS WOODS |
| Green Building Rough | 1/3/2023 | Approved | THOMAS WOODS |
| HVAC-Final | 1/3/2023 | Approved | THOMAS WOODS |
| PLUMBING-Final | 1/3/2023 | Approved | THOMAS WOODS |
| SGSOV-Seismic Gas S/O Valve | 1/3/2023 | SGSOV Approved | THOMAS WOODS |
| Smoke Detectors | 1/3/2023 | Approved | THOMAS WOODS |