10349 N CEDROS AVE 91345

Certificate Information: 10349 N CEDROS AVE 91345

Application / Permit
21014-20000-06077
Plan Check / Job No.
B21VN16867
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
10' X 13'-3" (133 SQ. FT.) ADDITION TO THE REAR OF THE (E) SFD. ALL WORK PER WFPP.
Permit Issued
Issued on 1/25/2022
Issuing Office
Current Status
CofO Issued on 3/20/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 12/7/2021 APPLICANT
Assigned to Plan Check Engineer 12/8/2021 OMAR GARNICA
Corrections Issued 12/8/2021 OMAR GARNICA
Plan Check Approved 1/12/2022 OMAR GARNICA
Building Plans Picked Up 1/14/2022 APPLICANT
Issued 1/25/2022 APPLICANT
CofO in Progress 6/15/2022 JENNIFER RABUCHIN
Permit Finaled 3/20/2023 DANIEL ORRANTE
CofO Issued 3/20/2023 DANIEL ORRANTE
Permit Finaled 3/20/2023 DANIEL ORRANTE

Permit Application Clearance Information

Roof/Waste drainage to street Cleared 12/23/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 12/23/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 12/27/2021 JOSE DUARTE-DIAZ

Contact Information

Contractor Carter Design & Remodeling Inc; Lic. No.: 932102-B 23890 COPPERHILL DRIVE #375      VALENCIA, CA 91354

Inspector Information

JOHN COLEMAN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI
JENNIFER RABUCHIN, (818) 374-1179 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Drilled-In Anchors 3/9/2022 Approved RYAN SALAZAR
Footing/Foundation/Slab 3/10/2022 Approved DEANDRE HOFFMAN
Floor/Roof Diaphrgm/Shear Wall 3/23/2022 Partial Approval JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 3/30/2022 Corrections Issued JENNIFER RABUCHIN
Floor/Roof Diaphrgm/Shear Wall 4/4/2022 Approved JENNIFER RABUCHIN
BUILDING-Rough-Frame 4/19/2022 Approved JENNIFER RABUCHIN
Green Building Rough 4/19/2022 Approved JENNIFER RABUCHIN
HVAC-Rough 4/19/2022 Approved JENNIFER RABUCHIN
Insulation 4/22/2022 Approved JENNIFER RABUCHIN
Insulation 4/26/2022 Approved JENNIFER RABUCHIN
Drywall Nailing 4/27/2022 Not Ready for Inspection JENNIFER RABUCHIN
Interior/Exterior Lathing 4/28/2022 Not Ready for Inspection JENNIFER RABUCHIN
Drywall Nailing 5/4/2022 Approved JENNIFER RABUCHIN
Interior/Exterior Lathing 5/10/2022 Approved DEANDRE HOFFMAN
ELECTRICAL-Final 6/14/2022 Approved JENNIFER RABUCHIN
Final 6/14/2022 OK to Issue CofO JENNIFER RABUCHIN
Green Building Final 6/14/2022 Approved JENNIFER RABUCHIN
HVAC-Final 6/14/2022 Approved JENNIFER RABUCHIN
PLUMBING-Final 6/14/2022 Approved JENNIFER RABUCHIN
SGSOV-Seismic Gas S/O Valve 6/14/2022 SGSOV Approved JENNIFER RABUCHIN
Smoke Detectors 6/14/2022 Approved JENNIFER RABUCHIN